Page 112 - Advances in Renewable Energies and Power Technologies
P. 112

4. Cost of Intermittence and Benefit of Forecasting  85




                     As a result, the overall relevant horizons of forecast should range from 5 min to
                  several days [30]. It is apparent that the time step of predicted data (daily or hourly
                  energy, 10-min or 20-min energy, etc.) varies depending on objectives and on fore-
                  casting horizon [25].




                  4. COST OF INTERMITTENCE AND BENEFIT OF FORECASTING
                  As seen before, deleting or reducing the “unpredictable” variations of ISRES re-
                  quires the use of energy storages and back-up energy production means able to
                  compensate immediately the power variations. As a consequence, backup generators
                  must often remain switched-on to maintain the production/consumption balance
                  promptly. Besides, PVand wind energy systems should be switched off, for example,
                  when their electrical production exceeds a certain percentage of the global produc-
                  tion (ISRES power curtailment). Such difficulties entail an additional production
                  cost compared with conventional production. The accurate prediction of ISRES
                  intermittence would represent a cost-effective access to these energy resources.
                  As the cost of the intermittence of solar and wind resources is quite important
                  [33,34], a reliable forecasting of these intermittences should not only allow to
                  manage more efficiently the overall electrical system but also significantly reduce
                  the negative cost impact of these ISRES on the electrical network; at last, the
                  cost-effectiveness of PV and wind energy systems is increased.
                     Evaluation and forecasting of ISRES power appears to be an essential tool for
                  renewable energy power plant developers to identify the location where ISRES
                  could be installed and to decrease the use of conventional electricity production
                  means as much as possible while optimizing the profitability of ISRES.


                  4.1 COST OF INTERMITTENCY
                  There are multiple reasons why the ISRES power variations are very troublesome:
                  because the purchase electricity contracts are set up in advance, because back-up
                  generators must be stopped or switched depending on the ISRES production varia-
                  tions, because some of them have to be operating even without producing to
                  compensate instantaneously the short production variations; all of them contribute
                  to the cost linked to variability.
                     Besides, ISRES production remains uncertain until the last moment, and as elec-
                  tricity trading takes place the day before delivery, the deviations between forecasted
                  and actual production have to be balanced on short notice, which is costly as well
                  [35]. Electrical systems need to incorporate additional flexibilities (new operational
                  practices, storage, demand-side flexibility, flexible generators, etc.) to adapt them-
                  selves to the constraints because of the variability of renewables.
                     The integration costs are evocated as “an increase in power system operating
                  costs” [36], as “the additional cost of accommodating wind and solar” [37],as
                  “the extra investment and operational cost of the non-ISRES part of the power
   107   108   109   110   111   112   113   114   115   116   117