                    Table l8
                    Example Case Capital Costs for Venturi Scrubbers
                    Cost item                                        Factor            Cost($)
                    Direct Costs, DC
                       Purchased Equipment Costs
                         Venturi scrubber and auxiliary equipment  As estimated, EC  $223,000
                         Instrumentation                      Included with EC       —
                         Sales tax                            0.03 EC                6,690
                         Freight                              0.05 EC                11.200
                           Purchased Equipment Cost, PEC      1.08 ECs               $241,000
                       Direct Installation Costs
                         Foundation and supports              0.06 PEC               $14,500
                         Erection and handling                0.40 PEC               96,400
                         Electrical                           0.01 PEC               2,400
                         Piping                               0.05 PEC               12,000
                         Insulation                           0.03 PEC               7,200
                         Painting                             0.01 PEC               2,400
                                                              0.56 PEC               $134,000
                       Site Preparation                       As required, SP
                       Building                               As required, Bldg.
                           Total Direct Cost, DC              1.56 PEC + SP + Bldg.  $375,000
                    Indirect Costs, IC
                       Engineering                            0.10 PEC               $24,000
                       Construction                           0.10 PEC               24,000
                       Contractor fee                         0.10 PEC               24,000
                       Start-up                               0.01 PEC               2,400
                       Performance test                       0.01 PEC               2,400
                       Contingency                            0.03 PEC               7,200
                         Total Indirect Cost, IC              0.35 PEC               $84,000
                    Total Capital Cost TCC = DC + IC          1.91 PEC + SP + Bldg.  $460,310 +
                                                                                       SP + Bldg.



                             Table 9 is used to determine the direct installation costs (1.56PEC), indirect costs
                             (0.35PEC), and total capital costs (TCC) of the Venturi scrubber system. The fac-
                             tors given in Table 9 are now used to estimate the TCC:
                               TCC = (1.56PEC + 0.35PEC) + SP + Building (Tables 9 and 18)
                               TCC = 1.91PEC + SP + Building
                               TCC = 1.91($241,000) + SP + Building
                               TCC = $460,310 + SP + Building

                             Because the site preparation (SP) cost and building cost are specific to each instal-
                             lation, these costs are not included in this example.

                       B. The direct annual costs include electric power cost, water, operating labor, and main-
                          tenance costs (Table 17).
                          1. Power (electricity) Cost: Use Eq. (23) to estimate the fan power requirements, F .
                                                                                             p
                             a. It assumed that 2 wk out of the year the factory utilizing the Venturi scrubber is
                               shut down for inventory and retooling, which provides annual operating period
   270   271   272   273   274   275   276   277   278   279   280