Page 392 -
P. 392

372   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM


                    PERT (Navy) and CPM  PERT was developed in the late 1950s specifically for the Polaris missile project
                    (Du Pont and Remington  in the USA. Many activities associatedwiththisproject hadnever been
                    Rand) differ because
                    they were developed by  attempted previously, so PERT was developed to handle uncertain activity times.
                    different people working  CPM was developed primarily for industrial projects for which activity times were
                    on different projects.  known. CPM offered the option of reducing activity times by adding more work-
                    Today, the best aspects  ers and/or resources, usually at an increased cost. So, a distinguishing feature of
                    of each have been
                    combined to provide a  CPM was that it identified trade-offs between time and cost for various project
                    valuable project  activities.
                    scheduling technique.  Today’s computerized versions of PERT and CPM combine the best features of
                                     both approaches. So, the distinction between the two techniques is no longer
                                     necessary. As a result, we refer to the project scheduling procedures covered in this
                                     chapter as PERT/CPM.




                               9.1    Project Scheduling With Known Activity Times


                    The effort that goes into  The owner of the Souk al Bustan (SaB) Shopping Centre in Dubai is planning to
                    identifying activities,  modernize and expand the current 32-business shopping centre complex. The proj-
                    determining      ect is expected to provide room for eight to ten new retail businesses. Financing has
                    interrelationships among
                    activities and estimating  been arranged through a private investor. All that remains is for the owner of the
                    activity times is crucial to  shopping centre to plan, schedule and complete the expansion project. Let us show
                    the success of PERT/  how PERT/CPM can help.
                    CPM. A significant  The first step in the PERT/CPM scheduling process is to develop a list of the
                    amount of time may be
                    needed to complete this  activities that make up the project. Table 9.1 shows the list of activities for the
                    initial phase of the  Shopping Centre expansion project. Nine activities are described and denoted
                    project scheduling  A through I for later reference. Table 9.1 also shows the immediate predecessor(s)
                    process.
                                     and the activity time (in weeks) for each activity. For a given activity, the immediate
                                     predecessor column identifies the activities that must be completed immediately
                    Immediate predecessor  prior to the start of that activity. Activities A and B do not have immediate prede-
                    information determines
                    whether activities can be  cessors and can be started as soon as the project begins; so, a dash is written in
                    completed in parallel  the immediate predecessor column for these activities. The other entries in the
                    (worked on       immediate predecessor column show that activities C, D and E cannot be started
                    simultaneously) or in  until activity A has been completed; activity F cannot be started until activity E
                    series (one completed
                    before another begins).  has been completed; activity G cannot be started until both activities D and F have
                    Generally, the more  been completed; activity H cannot be started until both activities B and C have been
                    series relationships  completed; and, finally, activity I cannot be started until both activities G and H have
                    present in a project, the  been completed. The project is finished when activity I is completed.
                    more time will be
                    required to complete the  The last column in Table 9.1 shows the number of weeks required to complete
                    project.         each activity. For example, activity A takes five weeks, activity B takes six weeks and
                                     so on. The sum of activity times is 51. As a result, you may think that the total time
                                     required to complete the project is 51 weeks. However, as we show, two or more
                    A project network is  activities may often be scheduled concurrently, so shortening the completion time
                    extremely helpful in
                    visualizing the  for the project. Ultimately, PERT/CPM will provide a detailed activity schedule for
                    interrelationships among  completing the project in the shortest time possible.
                    the activities. No rules  Using the immediate predecessor information in Table 9.1, we can construct a
                    guide the conversion of a  graphical representation of the project, or the project network. Figure 9.1 depicts
                    list of activities and
                    immediate predecessor  the project network for the Shopping Centre. The activities correspond to the nodes
                    information into a project  of the network (drawn as rectangles) and the arrows show the precedence relation-
                    network. The process of  ships among the activities. In addition, nodes have been added to the network to
                    constructing a project  denote the start and the finish of the project. A project network will help a manager
                    network generally
                    improves with practise  visualize the activity relationships and provide a basis for carrying out the PERT/
                    and experience.  CPM calculations.




                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   387   388   389   390   391   392   393   394   395   396   397