PROJECT SCHEDULING WITH KNOWN ACTIVITY TIMES  373



                       Table 9.1 List of Activities for the Souk Al Bustan Shopping Centre Project
                                       Activity                              Immediate             Activity
                       Activity        Description                           Predecessor         Time (weeks)

                       A               Prepare architectural drawings            —                    5
                       B               Identify potential new tenants            —                    6
                       C               Develop prospectus for tenants            A                    4
                       D               Select contractor                         A                    3
                       E               Prepare building permits                  A                    1
                       F               Obtain approval for building permits      E                    4
                       G               Perform construction                     D, F                 14
                       H               Finalize contracts with tenants          B, C                 12
                       I               Tenants move in                          G, H                  2
                                                                                                 Total 51




                                         There are a few things to note about the diagram. The first is that when you are
                                      drawing the diagram manually it will usually take several attempts before it is right,
                                      particularly with more complex projects. You should always check your diagram to
                                      make sure that the sequencing of activities is correct and that the precedence
                                      structure is correct. Secondly, the length of the arrows does not necessarily corre-
                                      spond to the actual time taken. The length of arrows is determined by how we need
                                      to show the diagram in terms of logical precedence of activities. Thirdly, this type of
                                      diagram is referred to as an activity-on-node diagram (or precedence diagram).
                                      An alternative approach is the activity-on-arrow diagram which is described in
                                      Appendix 9.1. In this chapter we focus on the activity-on-node approach primarily
                                      because this is the approach typically adopted by project management software such
                                      as Microsoft Project.

                                      The Concept of a Critical Path

                                      To facilitate the PERT/CPM calculations, we have modified the project network as
                                      shown in Figure 9.2. Note that the upper left-hand corner of each node contains the
                                      corresponding activity letter. The activity time appears immediately below the letter.




                      Figure 9.1 Project Network for the Souk al Bustan Shopping Centre


                                                     E           F
                                                   Prepare      Obtain
                                                   Permits     Permits
                                        A            D
                                      Prepare       Select                    G
                                     Drawings     Contractor               Construction

                                                     C           H                          I
                          Start                    Develop   Finalize Tenant              Tenants      Finish
                                                  Prospectus   Contracts                  Move In

                                        B
                                      Identify
                                    New Tenants






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   388   389   390   391   392   393   394   395   396   397   398