376   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM


                                     Figure 9.4 Determining the Earliest Start Time for Activity H


                                                             A  0        5
                                                                             Earliest finish time
                                                             5               for activity C is 9

                                                                           C  5        9  H
                                                   Start
                                                                           4            12
                                                             B  0         6
                                                             6                What are the earliest start and
                                                                                finish times for activity H?
                                                               Earliest finish time
                                                                for activity B is 6




                                     an activity time of 12 as shown in the node for activity H, the earliest finish time is
                                     EF ¼ ES + t ¼ 9+12 ¼ 21. The ES ¼ 9 and EF ¼ 21 values can now be entered
                                     in the node for activity H in Figure 9.4.
                                       Continuing with this forward pass through the network, we can establish the
                                     earliest start times and the earliest finish times for all activities in the network.
                                     Figure 9.5 shows the Shopping Centre project network with the ES and EF values
                                     for each activity. Note that the earliest finish time for activity I, the last activity in the
                                     project, is 26 weeks. Therefore, we now know that the total completion time for the
                                     project is 26 weeks.
                                       We now continue the algorithm for finding the critical path by making a back-
                                     ward pass through the network. Because the total completion time for the project is
                                     26 weeks, we begin the backward pass with a latest finish time of 26 for activity I.
                                     The latest finish time for an activity shows the latest time by which that activity must
                                     be finished if it is not to delay completion of the whole project. Once the latest finish
                                     time for an activity is known, the latest start time for an activity can be computed as
                                     follows. Let:
                                                           LS ¼ latest start time for an activity
                                                           LF ¼ latest finish time for an activity



                    Figure 9.5 Souk Al Bustan Shopping Centre Project Network with Earliest Start and Earliest Finish Times
                    Shown for all Activities


                                                E  5        6  F  6       10
                                                1           4

                                  A  0        5  D  5        8           G  10      24
                                  5             3                        14


                                                C  5        9  H  9       21           I  24      26
                        Start                                                                        Finish
                                                4          12                         2
                                                                                 EF = 26 for activity I; the
                                  B  0        6                                  project can be completed
                                  6                                              in 26 weeks.





                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   391   392   393   394   395   396   397   398   399   400   401