Page 399 -
P. 399

PROJECT SCHEDULING WITH KNOWN ACTIVITY TIMES  379



                       Table 9.2 Activity Schedule for the Souk Al Bustan Shopping Centre Project
                                     Earliest   Latest     Earliest    Latest
                                      Start      Start      Finish     Finish       Float
                       Activity       (ES)       (LS)        (EF)       (LF)      (LS   ES)    Critical Path?
                       A                0          0          5           5          0              Yes
                       B                0          6          6          12          6
                       C                5          8          9          12          3
                       D                5          7          8          10          2
                       E                5          5          6           6          0              Yes
                       F                6          6         10          10          0              Yes
                       G               10         10         24          24          0              Yes
                       H                9         12         21          24          3
                       I               24         24         26          26          0              Yes




                                      Such information is valuable in managing any project. Although larger projects
                                      usually increase the effort required to develop the immediate predecessor relation-
                                      ships and the activity time estimates, the procedure and contribution of PERT/CPM
                                      to larger projects are identical to those shown for the shopping centre expansion
                                      project.
                      Software packages such  Finally, computer packages may be used to carry out the steps of the PERT/CPM
                      as The Management  procedure. Figure 9.7 shows the activity schedule for the shopping centre expansion
                      Scientist perform the
                      critical path calculations  project developed by The Management Scientist software package. Input to the
                      quickly and efficiently.  program included the activities, their immediate predecessors and the expected
                      The project manager can  activity times. Only a few minutes were required to input the information and
                      modify any aspect of the  generate the critical path and activity schedule.
                      project and quickly
                      determine how the
                      modification affects the
                      activity schedule and the  Summary of the PERT/CPM Critical Path Procedure
                      total time required to
                      complete the project.  Before leaving this section, let us summarize the PERT/CPM critical path procedure.
                                         Step 1. Develop a list of the activities that make up the project.
                                         Step 2. Determine the immediate predecessor(s) for each activity in the project.
                                         Step 3. Estimate the completion time for each activity.
                                         Step 4. Draw a project network depicting the activities and immediate
                                               predecessors listed in steps 1 and 2.
                                         Step 5. Use the project network and the activity time estimates to determine the
                                               earliest start and the earliest finish time for each activity by making a
                                               forward pass through the network. The earliest finish time for the last
                                               activity in the project identifies the total time required to complete the
                                               project.
                                         Step 6. Use the project completion time identified in step 5 as the latest finish
                                               time for the last activity and make a backward pass through the network
                                               to identify the latest start and latest finish time for each activity.
                                         Step 7. Use the difference between the latest start time and the earliest start time
                                               for each activity to determine the slack for each activity.
                                         Step 8. Find the activities with zero slack; these are the critical activities.
                                         Step 9. Use the information from steps 5 and 6 to develop the activity schedule
                                               for the project.




                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   394   395   396   397   398   399   400   401   402   403   404