Page 403 -
P. 403
PROJECT SCHEDULING WITH UNCERTAIN ACTIVITY TIMES 383
Figure 9.9 Porta-Vac Cordless Vacuum Cleaner Project Network
F
C Cost
Routing
Estimates
A J
Prepare D G Final Finish
Design Prototype Testing Report
E H I
Start Marketing Market Pricing and
Brochure Survey Forecast
B
Plan Market
Research
Figure 9.10 Porta-Vac Project Network with Activity Times
C 5 8 F 8 10
3 8.5 11.5 2 11.5 13.5
A 0 5 D 5 9 G 9 12 J 13.5 15.5
Finish
5 0 5 4 5.5 9.5 3 9.5 13.5 2 13.5 15.5
E 5 8 H 8 11.5 I 11.5 13.5
Start
3 5 8 3.5 8 11.5 2 11.5 13.5
B 0 1.5
1.5 0 8
values rather than by one specific time estimate. In these instances, the uncertain
activity times are treated as random variables with associated probability distribu-
tions. As a result, probability statements will be provided about the ability to meet a
specific project completion date.
To incorporate uncertain activity times into the analysis, we need to obtain three
time estimates for each activity:
Optimistic time a ¼ the minimum activity time if everything progresses ideally
Most probable time m ¼ the most probable activity time under normal conditions
Pessimistic time b ¼ the maximum activity time if significant delays are encountered
To illustrate the PERT/CPM procedure with uncertain activity times, let us con-
sider the optimistic, most probable and pessimistic time estimates for the Porta-Vac
activities as presented in Table 9.4. Using activity A as an example, we see that the
most probable time is five weeks with a range from four weeks (optimistic) to 12
weeks (pessimistic). If the activity could be repeated a large number of times, what is
the average time for the activity? This average or expected time (t)isas follows:
Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.