Page 405 -
P. 405

PROJECT SCHEDULING WITH UNCERTAIN ACTIVITY TIMES  385


                                      Figure 9.11 Activity Time Distribution for Product Design (Activity A) for the Porta-Vac
                                      Project



                                                     Most probable           Expected (t)











                                                                                               Pessimistic
                                                  Optimistic

                                           0                4      5    6                              12
                                                             Activity Time (in Weeks)




                      When uncertain activity  The Critical Path
                      times are used, the
                      critical path calculations  When we have the project network and the expected activity times, we are ready to
                      will determine only the  proceed with the critical path calculations necessary to determine the expected time
                      expected or average time  required to complete the project and determine the activity schedule. In these
                      to complete the project.
                      The actual time required  calculations, we treat the expected activity times (Table 9.5) as the fixed length or
                      to complete the project  known duration of each activity. As a result, we can use the critical path procedure
                      may differ. However, for  introduced in Section 9.1 to find the critical path for the Porta-Vac project. After the
                      planning purposes, the  critical activities and the expected time to complete the project have been deter-
                      expected time should be
                      valuable information for  mined, we analyze the effect of the activity time variability.
                      the project manager.  Proceeding with a forward pass through the network shown in Figure 9.10, we can
                                      establish the earliest start (ES) and earliest finish (EF) times for each activity. Next,
                      Activities that have larger
                      variances show a greater  we make a backward pass through the network. The backward pass provides the
                      degree of uncertainty.  latest start (LS) and latest finish (LF) times shown in Figure 9.12. The project is now
                      The project manager  expected to take 17 weeks to complete.
                      should monitor the
                      progress of any activity
                      with a large variance
                      even if the expected time  Table 9.5 Expected Times and Variances for the Porta-Vac Project Activities
                      does not identify the
                      activity as a critical  Activity          Expected Time (weeks)           Variance
                      activity.
                                        A                                   6                     1.78
                                        B                                   2                     0.44
                                        C                                   3                     0.11
                                        D                                   5                     1.78
                                        E                                   3                     0.11
                                        F                                   2                     0.03
                                        G                                   3                     0.25
                                        H                                   4                     0.69
                                        I                                   2                     0.03
                                        J                                   2                     0.11
                                                                       Total 32






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   400   401   402   403   404   405   406   407   408   409   410