Page 410 -
P. 410

390   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM



                      Table 9.8 Activity Schedule for the Two-Machine Maintenance Project
                                  Earliest    Latest      Earliest     Latest
                                   Start       Start       Finish      Finish       Slack          Critical
                      Activity     (ES)        (LS)         (EF)        (LF)       (LS – ES)       Path?
                      A              0           0           7            7           0             Yes
                      B              7           7          10           10           0             Yes
                      C              0           1           6            7           1
                      D              6           7           9           10           1
                      E             10          10          12           12           0             Yes




                                     completion time. However, it is also evident that as we crash one activity, the slack
                                     time associated with other activities may change and therefore the critical path may
                                     change. Because of this we adopt an incremental approach to crashing by crashing
                                     one activity at a time and crashing by one day at a time. The overall purpose
                                     of crashing is to reduce the project duration while minimizing the extra costs. The
                                     first step is to pull together relevant information for each activity. This is shown in
                                     Table 9.9.
                                       For each activity, we show the normal activity time and the crash time. So, for
                                     example, we see that Activity A takes seven days to complete but it is possible to
                                     reduce this to four days. Similarly, Activity B takes three days but could be
                                     reduced to two. Next we show the normal cost of completing each activity and
                                     thecrashcost,withthedifferencebetweenthetwo beingtheextracosts incurred
                                     by crashing that activity. Activity A, for example, normally costs E500 to com-
                                     pletebut couldbedonemorequickly foratotalcostof E800. The next column
                                     shows the maximum possible reduction in activity time (the Normal time minus
                                     the Crash time). Finally we show the crash cost per day calculated as the extra
                                     costs incurred by crashing divided by the maximum reduction in time possible
                                     through crashing. So, again for Activity A, the extra crash cost is E300 divided
                                     by three days or E100 per day. We make the simplifying assumption that there is
                                     a linear relationship between crash costs and crash time. Now we have the
                                     information we need, we can proceed to crash the project. To reduce overall project
                                     duration we only need to consider those activities that are currently critical: A,B,E.
                                     Of these, Activity A has the lowest crash cost per day so is to be preferred given
                                     that we want to reduce project completion time while minimizing any extra cost.




                      Table 9.9 Normal and Crash Activity Data for the Two-Machine Maintenance Project

                                                                                                  Crash
                                                                                   Maximum
                                                                                                  Cost
                                                                                  Reduction
                                     Time (days)             Total Cost E                        per Day
                                                                                    in Time          0
                                                                                                     i
                                                                            0
                      Activity    Normal     Crash    Normal (C i )  Crash (C i )    (M i )      K i ¼  C  C i
                                                                                                      M i
                      A              7         4          500           800           3           E100
                      B              3         2          200           350           1             150
                      C              6         4          500           900           2             200
                      D              3         1          200           500           2             150
                      E              2         1          300           500           1             200





                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   405   406   407   408   409   410   411   412   413   414   415