394   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM



                     Problems


                                 1 The Mohawk Discount Store is designing a management training programme for staff at its
                                    corporate headquarters. The company wants to design the programme so that trainees can
                                    complete it as quickly as possible. Important precedence relationships must be maintained
                                    between assignments or activities in the programme. For example, a trainee cannot serve as an
                                    assistant to the store manager until the trainee has obtained experience in the credit
                                    department and at least one sales department. The following activities are the assignments that
                                    must be completed by each trainee in the programme. Construct a project network for this
                                    problem. Do not perform any further analysis.



                                  Activity                 A    B     C      D      E     F      G      H
                                  Immediate Predecessor    —    —     A     A,B    A, B   C     D,F    E,G



                                 2 Bridge City Developers is coordinating the construction of an office complex. As part of the
                                    planning process, the company generated the following activity list. Draw a project network
                                    that can be used to assist in the scheduling of the project activities.


                                  Activity                A   B    C    D     E    F   G   H    I      J
                                  Immediate Predecessor  —    —    —   A, B  A, B  D   E   C   C    F, G, H, I


                                 3 Construct a project network for the following project. The project is completed when
                                    activities F and G are both complete.

                                  Activity                  A      B     C      D      E       F        G

                                  Immediate Predecessor     —      —     A      A     C, B     C, B    D, E


                                 4 Assume that the project in Problem 3 has the following activity times (in months).

                                  Activity       A        B         C        D        E         F        G
                                  Time           4        6         2        6         3        3        5

                                    a. Find the critical path.
                                    b. The project must be completed in one-and-a-half years. Do you anticipate difficulty in
                                      meeting the deadline? Explain.

                                 5 Management Decision Systems (MDS) is a consulting company that specializes in the
                                    development of decision support systems. MDS obtained a contract to develop a computer
                                    system to assist the management of a large company in formulating its capital expenditure
                                    plan. The project leader developed the following list of activities and immediate
                                    predecessors. Construct a project network for this problem.

                                  Activity                A    B    C    D   E   F     G     H      I    J
                                  Immediate Predecessor   —    —    —    B   A   B    C, D  B, E   F, G  H





                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   409   410   411   412   413   414   415   416   417   418   419