CONSIDERING TIME–COST TRADE-OFFS  397


                                      a. Calculate the expected activity completion times and the variance for each
                                        activity.
                                      b. An analyst determined that the critical path consists of activities B–D–F. Calculate the
                                        expected project completion time and the variance.
                                  11 Suppose that the following estimates of activity times (in weeks) were provided for the
                                      network shown in Problem 6.


                                           Activity     Optimistic      Most Probable      Pessimistic
                                           A                4.0              5.0               6.0
                                           B                2.5              3.0               3.5
                                           C                6.0              7.0               8.0
                                           D                5.0              5.5               9.0
                                           E                5.0              7.0               9.0
                                           F                2.0              3.0               4.0
                                           G                8.0              10.0              12.0
                                           H                6.0              7.0               14.0



                                      What is the probability that the project will be completed
                                      a. Within 21 weeks?
                                      b. Within 22 weeks?
                                      c. Within 25 weeks?
                                  12 Andreas Bierhoff is in charge of planning and coordinating next spring’s sales
                                      management training programme for his company. Andreas listed the following activity
                                      information for this project.


                                                          Immediate                Time (weeks)
                       Activity  Description             Predecessor   Optimistic  Most Probable  Pessimistic
                       A         Plan topic                   —           1.5           2.0           2.5
                       B         Obtain speakers              A           2.0           2.5           6.0
                       C         List meeting locations       —           1.0           2.0           3.0
                       D         Select location              C           1.5           2.0           2.5
                       E         Finalize speaker travel plans  B, D      0.5           1.0           1.5
                       F         Make final check with        E           1.0           2.0           3.0
                                   speakers
                       G         Prepare and mail            B, D         3.0           3.5           7.0
                                   brochure
                       H         Take reservations            G           3.0           4.0           5.0
                       I         Handle last-minute          F, H         1.5           2.0           2.5
                                   details


                                      a. Draw a project network.
                                      b. Prepare an activity schedule.
                                      c. What are the critical activities and what is the expected project completion time?
                                      d. If Andreas wants a 0.99 probability of completing the project on time, how far ahead of
                                        the scheduled meeting date should he begin working on the project?







                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   412   413   414   415   416   417   418   419   420   421   422