                                   6 Consider the following project network and activity times (in weeks).


                                                                 C                      H

                                                      A

                                                                 D           F                    Finish
                                          Start


                                                      B          E           G





                                    Activity     A       B        C       D       E       F       G        H
                                    Time         5        3       7       6       7       3       10       8


                                      a. Identify the critical path.
                                      b. How much time will be needed to complete this project?
                                      c. Can activity D be delayed without delaying the entire project? If so, by how many
                                        weeks?
                                      d. Can activity C be delayed without delaying the entire project? If so, by how many
                                        weeks?
                                      e. What is the schedule for activity E?
                                   7 A project involving the installation of a computer system comprises eight activities. The
                                      following table lists immediate predecessors and activity times (in weeks).

                                              Activity          Immediate Predecessor          Time

                                                A                       —                       3
                                                B                       —                       6
                                                C                       A                       2
                                                D                      B, C                     5
                                                E                       D                       4
                                                F                       E                       3
                                                G                      B, C                     9
                                                H                      F, G                     3


                                      a. Draw a project network.
                                      b. What are the critical activities?
                                      c. What is the expected project completion time?
                                   8 Khobar Technical College is considering building a new multipurpose athletic
                                      complex on campus. The complex would provide a new gymnasium for intercollegiate
                                      basketball games, expanded office space, classrooms and intramural facilities.
                                      The following activities would have to be undertaken before construction can begin.











                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   410   411   412   413   414   415   416   417   418   419   420