400   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM





                                    Develop a complete activity schedule based on the crashed activity times.

                                17 Consider the following project network and activity times (in days).


                                                   A           C            E


                                       Start                                                     Finish


                                                   B           D            F           G



                                  Activity       A        B         C        D        E         F        G
                                  Time           3        2         5        5        6         2        2


                                    The crashing data for this project are as follows.

                                                         Time (days)                        Cost (E)
                                  Activity         Normal           Crash           Normal           Crash

                                  A                   3               2                800            1 400
                                  B                   2               1              1 200            1 900
                                  C                   5               3              2 000            2 800
                                  D                   5               3              1 500            2 300
                                  E                   6               4              1 800            2 800
                                  F                   2               1                600            1 000
                                  G                   2               1                500            1 000


                                    a. Find the critical path and the expected project completion time.
                                    b. What is the total project cost using the normal times?
                                    c. What is the expected project completion time and cost with crashing?
                                18 Office Automation developed a proposal for introducing a new computerized office system that
                                    will improve word processing and interoffice communications for a particular company.
                                    Contained in the proposal is a list of activities that must be accomplished to complete the new
                                    office system project. Use the following relevant information about the activities.
                                                                        Time (weeks)        Cost (E1000s)

                                                        Immediate
                     Activity   Description            Predecessor    Normal    Crash     Normal     Crash

                     A          Plan needs                 —            10        8          30        70
                     B          Order equipment             A            8        6         120       150
                     C          Install equipment           B           10        7         100       160
                     D          Set up training lab         A            7        6          40        50
                     E          Conduct training course     D           10        8          50        75
                     F          Test system               C, E           3        3          60        —






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   415   416   417   418   419   420   421   422   423   424   425