ACTIVITY ON ARROW NETWORKS  403



                       Table 9.1 List of Activities for the Souk Al Bustan Shopping Centre Project
                                       Activity                              Immediate             Activity
                       Activity        Description                           Predecessor         Time (weeks)

                       A               Prepare architectural drawings            —                    5
                       B               Identify potential new tenants            —                    6
                       C               Develop prospectus for tenants            A                    4
                       D               Select contractor                         A                    3
                       E               Prepare building permits                  A                    1
                       F               Obtain approval for building permits      E                    4
                       G               Perform construction                     D, F                 14
                       H               Finalize contracts with tenants          B, C                 12
                       I               Tenants move in                          G, H                  2
                                                                                                 Total 51




                                      Figure 9.16 Activity A

                                                                   A Prepare Drawings
                                                           1                            2
                                                                         5



                                      diagram activity by activity as we move to the right checking that the precedences in
                                      the diagram are consistent with the project information. Figure 9.17 shows the first
                                      part of the AOA diagram up to activity C. Activities A and B both start from Node 1
                                      (the start of the project). Activity C starts after Activity A. You should be able to see
                                      why we have shown the B and C arrows going into Node 3. Eventually Activity H will
                                      be shown on the arrow coming out of Node 3 since H is dependent on both B and C.
                                         The complete AOA diagram for this project is shown in Figure 9.18. You should
                                      check the diagram carefully to see that all the dependencies are consistent with the
                                      project information given. Note also that some of the arrows have been highlighted
                                      to show the critical path through the network. In addition, we have added time
                                      information into each node as is usual with the AOA diagram. So, Node 3 for
                                      example shows that at this time Activities A,B,C are complete and will take 9 weeks
                                      to complete (the first of the two times shown). This is the earliest finish time, EFT,
                                      for this part of the network. The second figure of 12 shows the latest finish time,
                                      LFT. These times are obtained from the completed network diagram with the usual
                                      forward pass to obtain the EFTs for each node and then a backward pass to obtain
                                      the LFTs. We see again from Node 7 that the project will take 26 weeks to complete.


                                      Figure 9.17 Activities A,B,C


                                                                                        3
                                                                       B
                                                                        6         C  4
                                                                      A
                                                            1                  2
                                                                      5






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   418   419   420   421   422   423   424   425   426   427   428