Page 422 -
P. 422

402   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM





                      Managerial Report
                      Develop a report that presents the activity schedule and expected project completion time for the warehouse
                      expansion project. Include a project network in the report. In addition, take into consideration the following
                      issues.
                      1 R.C. Coleman’s top management established a required 40-week completion time for the project. Can this
                         completion time be achieved? Include probability information in your discussion. What recommendations
                         do you have if the 40-week completion time is required?
                      2 Suppose that management requests that activity times be shortened to provide an 80 per cent chance of
                         meeting the 40-week completion time. If the variance in the project completion time is the same as you
                         found in part (1), by how much should the expected project completion time be shortened to achieve the
                         goal of an 80 per cent chance of completion within 40 weeks?
                      3 Using the expected activity times as the normal times and the following crashing information, determine the
                         activity crashing decisions and revised activity schedule for the warehouse expansion project.

                                                                                     Cost (E)
                            Activity       Crashed Activity Time (weeks)      Normal         Crashed

                            A                           4                      1 000           1 900
                            B                           7                      1 000           1 800
                            C                           2                      1 500           2 700
                            D                           8                      2 000           3 200
                            E                           7                      5 000           8 000
                            F                           4                      3 000           4 100
                            G                           5                      8 000          10 250
                            H                           4                      5 000           6 400
                            I                           4                     10 000          12 400
                            J                           3                      4 000           4 400
                            K                           3                      5 000           5 500





                      Appendix 9.1    Activity on Arrow Networks


                                     In this chapter we have used the activity on node (AON) approach to project
                                     networks. As mentioned, an alternative approach is to construct an activity-on-arrow
                                     (AOA) network diagram. In this appendix we briefly explain this type of network
                                     diagram. We will use the Shopping Centre example that we introduced in
                                     Section 9.1. We show Table 9.1 again with the relevant information.
                                       With AON network diagrams the activities are shown at the nodes and the arrows
                                     show the dependencies between activities. In an AOA diagram we use the arrows to
                                     show activities being undertaken and the nodes represent moments in time when an
                                     activity starts or finishes. To illustrate look at Figure 9.16. This shows part of an
                                     AOA diagram for Activity A. Node 1 represents the start of Activity A and Node 2
                                     represents the time Activity A is completed. The arrow itself shows Activity A being
                                     undertaken with the time needed shown underneath, five weeks.
                                       Construction of an AOA network diagram follows much the same idea as for an
                                     AON diagram. We start at the left with the start of the project and construct the






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   417   418   419   420   421   422   423   424   425   426   427