Page 411 -
P. 411

CONSIDERING TIME–COST TRADE-OFFS  391



                        MANAGEMENT SCIENCE IN ACTION



                        Kimberly-Clark Europe
                            imberly-Clark are a leading global health and  to: project management lacking standards and dis-
                        K hygiene company employing almost 60000 staff  cipline; roles and responsibilities being unclear;
                        worldwide and with sales of nearly $16 billion in 2005.  unrealistic timescales being set. The company
                        It has operations in 37 countries and sells in more  decidedonaninitiativetoestablish commonproj-
                        than 150 countries. However, in the late 1990s its  ect management approaches across Kimberly-
                        European business was facing difficulties. Although  Clark Europe supported by extensive staff training.
                        its UK business was strong, the company were keen  As a result the company is now confident that the
                        to expand market share across the rest of Europe,  selection of projects is improved and that those
                        but a number of critical projects had not   projects are being managed effectively with signifi-
                        been completed successfully and were affecting  cant cost savings being achieved.
                        the company’s results to the extent that a
                                                                    Based on M. Palmer, ‘How an effective project culture can help to achieve
                        profits warning was issued. An independent review  business success: Establishing a project culture in Kimberly-Clark
                        concluded that there were major problems relating  Europe’, Industrial and Commercial Training, 34/3 (2002): 101–105.



                                      So we crash Activity A by one day at a cost of E100. This will reduce the overall
                                      completion time from the current 12 days to 11 days. However, we can crash
                                      Activity A still further given that there are a further two crash days available.
                                      However, crashing Activity A by one day may have affected the slack times of
                                      other activities and may have altered the critical path so we need to check the
                                      network. On inspection of Figure 9.14 we can see that the A–B part of the network
                                      will now have a duration of nine days (six+three) and that of the C–D part of the
                                      network will also have a total duration of nine days (six+three). We now have a
                                      situation whereby, through crashing Activity A, all activities are now critical. Clearly
                                      crashing Activity A by a further day will not reduce the overall project duration
                                      time since the path C–D will still take nine days. Clearly, if we were to crash part of
                                      the A–B path by one day we would simultaneously have to crash part of the C–D
                                      path by one day. The net effect on total project duration, however, would only be
                                      one day. In fact we can summarize the crashing options we now have:


                                                   Activities to be crashed      Total crash costs
                                                   A and C                       E300 (E100 + E200)
                                                   A and D                       E250 (E100 + E150)
                                                   B and C                       E350 (E150 + E200)
                                                   B and D                       E300 (E150 + E150)
                                                   E                             E200



                      The Project Management  We now see that the lowest cost option is to crash Activity E next. This will reduce
                      Institute (PMI) was  total project duration by a further day, to ten days, at an extra cost of E200. We have
                      formed in 1969 to
                      provide a forum for the  now met the hospital manager’s target of completing the maintenance in ten days
                      project management  but we should inform her that this will cost an extra E300. If any further reductions
                      community.      are needed, we could simply continue crashing activities using the information
                                      above. In this example, crashing can be conducted with some basic calculations
                                      and careful inspection of the project network. For more complex projects, crashing
                                      would normally be done as part of the computer software solution.




                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   406   407   408   409   410   411   412   413   414   415   416