Page 408 -
P. 408

388   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM


                                     Figure 9.14 Probability the Porta-Vac Project Will Meet the 20-Week Deadline




                                                                                 at T = 20
                                                        = 1.65 weeks             z =  20 – 17  = 1.82
                                                                                     1.65

                                                                     P(T  20)


                                                                                               T
                                                                       17        20
                                                                   Time (weeks)




                                     Using z ¼ 1.82 and the table for the normal distribution (see Appendix A), we find
                                     that  the  probability  of  the  project  meeting  the  20-week  deadline  is
                                     0.4656 + 0.5000 ¼ 0.9656. Thus, even though activity time variability may cause
                                     the completion time to exceed 17 weeks, calculations indicate a high probability
                                     that the project will be completed before the 20-week deadline. Similar probability
                                     calculations can be made for other project deadline alternatives.




                      NOTES AND COMMENTS


                         or projects involving uncertain activity times, the  critical activities may cause an original noncritical
                      F probability that the project can be completed  activity to become critical and hence increase the time
                      within a specified amount of time is helpful manage-  required to complete the project. By frequently mon-
                      rial information. However, remember that this pro-  itoring the progress of the project to make sure all
                      bability estimate is based only on the critical  activities are on schedule, the project manager will be
                      activities. When uncertain activity times exist, longer-  better prepared to take corrective action if a noncritical
                      than-expected completion times for one or more non-  activity begins to lengthen the duration of the project.







                               9.3    Considering Time–Cost Trade-Offs


                                     The original developers of CPM provided the project manager with the option of
                                     adding resources to selected activities to reduce project completion time. Added
                                     resources (such as more workers, overtime and so on) generally increase project
                                     costs, so the decision to reduce activity times must take into consideration the
                                     additional cost involved. In effect, the project manager must make a decision that
                    Using more resources to  involves trading reduced activity time for additional project cost.
                    reduce activity times was  Consider a scenario in a hospital. In one of the surgical clinics, two specialist
                    proposed by the  machines periodically have to undergo routine maintenance. While this is being
                    developers of CPM. The
                    shortening of activity  done, medical operations are halted and clearly the hospital manager is keen for the
                    times is referred to as  time needed for maintenance to be as short as possible. Table 9.7 summarizes the
                    crashing.        key activities involved in this project. Because management has had substantial




                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   403   404   405   406   407   408   409   410   411   412   413