Page 402 -
P. 402

382   CHAPTER 9 PROJECT SCHEDULING: PERT/CPM


                                     time. In such situations we need to be able to deal with uncertainty in activity
                                     completion times. We shall show how we do this with the following example.
                                     The Daugherty Porta-Vac Project

                    Accurate activity time  The H.S. Daugherty Company in Ireland has manufactured industrial vacuum
                    estimates are important  cleaning systems for many years. Recently, a member of the company’s new-product
                    in the development of an  research team submitted a report suggesting that the company consider manufactur-
                    activity schedule. When
                    activity times are  ing a cordless vacuum cleaner. The new product, referred to as Porta-Vac, could
                    uncertain, the three time  contribute to Daugherty’s expansion into the household market. Management hopes
                    estimates – optimistic,  that it can be manufactured at a reasonable cost and that its portability and no-cord
                    most probable and  convenience will make it extremely attractive.
                    pessimistic – allow the
                    project manager to take  Daugherty’s management wants to study the feasibility of manufacturing the Porta-
                    uncertainty into  Vac product. The feasibility study will recommend the action to be taken. To complete
                    consideration in  this study, information must be obtained from the firm’s research and development
                    determining the critical  (R&D), product testing, manufacturing, cost estimating and market research groups.
                    path and the activity
                    schedule. This approach  How long will this feasibility study take? In the following discussion, we show how to
                    was developed by the  answer this question and provide an activity schedule for the project.
                    designers of PERT.  Again, the first step in the project scheduling process is to identify all activities
                                     that make up the project and then determine the immediate predecessor(s) for each
                                     activity. Table 9.3 shows these data for the Porta-Vac project.
                                       The Porta-Vac project network is shown in Figures 9.9 and 9.10. Verify that the
                                     network does in fact maintain the immediate predecessor relationships shown in
                                     Table 9.3.
                                     Uncertain Activity Times

                                     However, suppose that the manager in charge of this project has now been informed
                                     that some of the activity times are not guaranteed but are best estimates. After all,
                                     this is quite likely in the real world. Unpredictable factors may affect the completion
                                     of a particular activity: it may take longer than we thought or sometimes we may be
                                     able to complete it earlier than expected. How will this affect the project network,
                                     the current critical path and overall project completion? If we consider Activity A,
                                     for example, which is currently on the critical path, we may now be informed that the
                                     most likely activity time is five weeks but that it could take as long as 12 weeks or, if
                                     everything goes well, we might finish this activity in four weeks. In fact, in many
                                     cases, activity times are uncertain and are best described by a range of possible


                      Table 9.3 Activity List for the Porta-Vac Project

                                                                              Immediate           Activity
                      Activity     Description                               Predecessor       Time (weeks)

                      A            Develop product design                         —                 5
                      B            Plan market research                           —                 1.5
                      C            Prepare routing (manufacturing engineering)    A                 3
                      D            Build prototype model                          A                 4
                      E            Prepare marketing brochure                     A                 3
                      F            Prepare cost estimates (industrial engineering)  C               2
                      G            Do preliminary product testing                 D                 3
                      H            Complete market survey                        B, E               3.5
                      I            Prepare pricing and forecast report            H                 2
                      J            Prepare final report                          F, G, I            2






                Copyright 2014 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s). Editorial review has
                      deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   397   398   399   400   401   402   403   404   405   406   407