Page 181 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 181

Chapter 7 Estimation of Capital Costs







                    I n Chapter  1,  the  information  provided  on  a  process  flow  diagram,  including  a  stream  table  and  an
                    equipment summary table, was presented. In the next four chapters, this information will be used as a
                    basis for estimating

                          1.   How much money (capital cost) it takes to build a new chemical plant
                          2.   How much money (operating cost) it takes to operate a chemical plant
                          3.   How to combine items 1 and 2 to provide several distinct types of composite values reflecting
                                process profitability
                          4.   How to select a “best process” from competing alternatives
                          5.   How to estimate the economic value of making process changes and modifications to an existing
                                processes
                          6.   How to quantify uncertainty when evaluating the economic potential of a process


                    In  this  chapter,  we  concentrate  on  the  estimation  of  capital  costs. Capital  cost  pertains  to  the  costs
                    associated with construction of a new plant or modifications to an existing chemical manufacturing plant.


                    7.1 Classifications of Capital Cost Estimates





                    There  are  five  generally  accepted  classifications  of  capital  cost  estimates  that  are  most  likely  to  be
                    encountered in the process industries [1,2,3]:
                          1.   Detailed estimate
                          2.   Definitive estimate
                          3.   Preliminary estimate
                          4.   Study estimate

                          5.   Order-of-magnitude estimate

                    The information required to perform each of these estimates is provided in Table 7.1.


                    Table 7.1 Summary of Capital Cost Estimating Classifications (References [1], [2], and [3])



                    Order-of-Magnitude (also known as Ratio or Feasibility) Estimate


                    Data:  This  type  of  estimate  typically  relies  on  cost  information  for  a  complete  process  taken  from
                    previously  built  plants.  This  cost  information  is  then  adjusted  using  appropriate  scaling  factors,  for
                    capacity, and for inflation, to provide the estimated capital cost.


                    Diagrams: Normally requires only a block flow diagram.



                    Study (also known as Major Equipment or Factored) Estimate


                    Data: This type of estimate utilizes a list of the major equipment found in the process. This includes all
   176   177   178   179   180   181   182   183   184   185   186