Page 184 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 184

definition are at the high end, then the expected cost range would be between $1.76 and $2.36 million. If
                    the effort and definition are at the low end, then the expected cost range would be between $1.04 and
                    $3.44 million.


                    The  primary  reason  that  capital  costs  are  underestimated  stems  from  the  failure  to  include  all  of  the
                    equipment needed in the process. Typically, as a design progresses, the need for additional equipment is
                    uncovered, and the estimate accuracy improves. The different ranges of cost estimates are illustrated in
                    Example 7.2.


                    Example 7.2



                    Compare the costs for performing an order-of-magnitude estimate and a detailed estimate for a plant that
                                    6
                    cost $5.0 × 10  to build.

                    For the order-of-magnitude estimate, the cost of the estimate is in the range of 0.015% to 0.3% of the final
                    cost of the plant:
                                                                   6
                          Highest Expected Value: ($5.0 × 10 )(0.003) = $15,000
                                                                  6
                          Lowest Expected Value: ($5.0 × 10 )(0.00015) = $750

                    For the detailed estimate, the cost of the estimate is in the range of 10 to 100 times that of the order-of-
                    magnitude estimate.


                    For the lowest expected cost range:
                                                                   6
                          Highest Expected Value: ($5.0 × 10 )(0.03) = $150,000
                                                                  6
                          Lowest Expected Value: ($5.0 × 10 )(0.0015) = $7500

                    For the highest expected cost range:
                                                                   6
                          Highest Expected Value: ($5.0 × 10 )(0.3) = $1,500,000
                                                                  6
                          Lowest Expected Value: ($5.0 × 10 )(0.015) = $75,000

                    Capital cost estimates are essentially paper-and-pencil studies. The cost of making an estimate indicates
                    the personnel hours required in order to complete the estimate. From Table 7.2 and Examples 7.1 and 7.2,
                    the trend between the accuracy of an estimate and the cost of the estimate is clear. If greater accuracy is
                    required  in  the  capital  cost  estimate,  then  more  time  and  money  must  be  expended  in  conducting  the
                    estimate.  This  is  the  direct  result  of  the  greater  detail  required  for  the  more  accurate  estimating
                    techniques.


                    What cost estimation technique is appropriate? At the beginning of Chapter 1, a short narrative was given
                    that  introduced  the  evolution  of  a  chemical  process  leading  to  the  final  design  and  construction  of  a
                    chemical plant. Cost estimates are performed at each stage of this evolution.


                    There are many tens to hundreds of process systems examined at the block diagram level for each process
                    that makes it to the construction stage. Most of the processes initially considered are screened out before
                    any  detailed  cost  estimates  are  made.  Two  major  areas  dominate  this  screening  process.  To  continue
                    process development, the process must be both technically sound and economically attractive.


                    A typical series of cost estimates that would be carried out in the narrative presented in Chapter 1 is as
   179   180   181   182   183   184   185   186   187   188   189