Page 182 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 182

pumps,  compressors  and  turbines,  columns  and  vessels,  fired  heaters,  and  exchangers.  Each  piece  of
                    equipment  is  roughly  sized  and  the  approximate  cost  determined.  The  total  cost  of  equipment  is  then
                    factored to give the estimated capital cost.


                    Diagrams: Based on PFD as described in Chapter 1. Costs from generalized charts.


                    Note: Most individual student designs are in this category.



                    Preliminary Design (also known as Scope) Estimate


                    Data: This type of estimate requires more accurate sizing of equipment than used in the study estimate. In
                    addition, approximate layout of equipment is made along with estimates of piping, instrumentation, and
                    electrical requirements. Utilities are estimated.


                    Diagrams:  Based  on  PFD  as  described  in Chapter  1.  Includes  vessel  sketches  for  major  equipment,
                    preliminary plot plan, and elevation diagram.


                    Note: Most large student group designs are in this category.



                    Definitive (also known as Project Control) Estimate


                    Data:  This  type  of  estimate  requires  preliminary  specifications  for  all  the  equipment,  utilities,
                    instrumentation, electrical, and off-sites.


                    Diagrams:  Final  PFD,  vessel  sketches,  plot  plan,  and  elevation  diagrams,  utility  balances,  and  a
                    preliminary P&ID.



                    Detailed (also known as Firm or Contractor’s) Estimate


                    Data: This type of estimate requires complete engineering of the process and all related off-sites and
                    utilities. Vendor quotes for all expensive items will have been obtained. At the end of a detailed estimate,
                    the plant is ready to go to the construction stage.


                    Diagrams: Final PFD and P&ID, vessel sketches, utility balances, plot plan and elevation diagrams, and
                    piping isometrics. All diagrams are required to complete the construction of the plant if it is built.


                    The five classifications given in Table 7.1 roughly correspond to the five classes of estimate defined in
                    the AACE  Recommended  Practice  No.  17R-97  [4].  The  accuracy  range  and  the  approximate  cost  for
                    performing each class of estimate are given in Table 7.2.


                    Table 7.2 Classification of Cost Estimates
   177   178   179   180   181   182   183   184   185   186   187