Page 43 - Analysis, Synthesis and Design of Chemical Processes, Third Edition
P. 43

Process: Duty, Area, Temperature, and Pressure for both streams


                                                             Number of Shell and Tube Passes


                                                        Materials of Construction: Tubes and Shell



                                                                     Tanks and Vessels



                                   Height, Diameter, Orientation, Pressure, Temperature, Materials of Construction



                                                                            Pumps



                        Flow, Discharge Pressure, Temperature, ΔP, Driver Type, Shaft Power, Materials of Construction



                                                                        Compressors



                                       Actual Inlet Flowrate, Temperature, Pressure, Driver Type, Shaft Power,
                                                                  Materials of Construction




                                                                       Heaters (Fired)



                                    Type, Tube Pressure, Tube Temperature, Duty, Fuel, Material of Construction



                                                                             Other



                                                                Provide Critical Information


                    The information presented in Table 1.6 is used in preparing the equipment summary portion of the PFD
                    for the benzene process. The equipment summary for the benzene process is presented in Table 1.7, and
                    details of how we estimate and choose various equipment parameters are discussed in Chapter 11.


                    Table 1.7 Equipment Summary for Toluene Hydrodealkylation PFD