                                           Optimizing Boiler Plants

                                        Establishing the Ideal Scene










                     Optimizing the performance of boiler plants    economic  evaluations and justifying additional
                and distribution systems is a broad and rewarding   personnel and modifications to existing systems.
                subject. On the surface you might think it requires      The  next  step  will  be  to  tune-up  the  boiler
                a  great  deal  of  knowledge  and  insight.  It  covers   and accomplish any maintenance and repair iden-
                many engineering subjects and involves an un-       tified during the initial testing to bring it back, as
                derstanding of the dynamics of operating systems    close as reasonably possible, to its original design
                composed of many subsystems and components.         performance level.
                If the job is approached on a systematic basis, it
                is much simpler and you will be more successful.    ————————————————————————
                This book is organized for a systematic and simple   Tuned-up efficiency is the efficiency after operating adjust-
                approach to boiler plant optimization.              ments,  lowering  excess  air,  and  minor  repairs  have  been
                                                                    completed. This will be the baseline efficiency for estimating
                ————————————————————————                            all future savings.
                As-found efficiency is the efficiency for a boiler in its exist-  ————————————————————————
                ing state of repair and maintenance. This efficiency will be
                used as the baseline for any later efficiency improvements.      There are many minor problems which can
                It is very important that the as-found efficiency be recorded   develop during the life of a boiler and distribu-
                because it will serve as a benchmark to estimate the value of   tion systems that cause non-optimum perfor-
                a Boiler Optimization program                       mance. Over time, they can waste a great deal of
                ————————————————————————                            energy.
                                                                         To make an honest and accurate evaluation
                     The beginning point for Boiler Plant Optimi-   of the potential savings available, all equipment
                zation Program is to establish the as found efficiency   must be in a normal state of repair with the boiler
                for each boiler and system. This information will   air/fuel ratios at designed levels. If this is not the
                serve as a datum to show the expected benefits of   case,  estimates  of  savings  and  justifications  for
                the program.                                        new  equipment  and  modifications  will  contain
                     It may be that millions of dollars can be      false information leading to poor decisions.
                saved by improving plant and distribution sys-           It  is  very  important  that  the  tuned-up  effi-
                tem efficiency. The as-found conditions will serve   ciency be accurate, because the economic benefits
                as a datum for establishing this fact and also il-  of  improvement  options  will  be  estimated  from
                lustrate the folly of neglecting boilers and their   this efficiency.
                energy distribution systems to management and            Next, there should be an estimate of the sav-
                decision makers.                                    ings if the efficiency were to be improved to a rea-
                     Also, if the plant is found to be efficient, it will   sonable level. This information is used to deter-
                bring credit to those responsible for the plant. In   mine if further work on a boiler is justified and to
                any case the as-found efficiency is important for   set priorities for competing projects.