Page 20 - Chemical process engineering design and economics
P. 20

Processes and Process Engineering                               7


                 At the  end  of the pilot-scale tests, the  process  is again evaluated, but  since
            the process-design phase of the project will require a substantial increase in capital
            investment, the calculations require improved  accuracy.  Table  1.2 lists the activi-
            ties  of the process-design engineer. Usually, there  are  several  technically  accept-
            able  alternatives  available  for each process unit,  so that  the  process-design engi-
            neer  will  have  to  evaluate  these  alternatives  to  determine  the  most  economical
            design.  Additionally, each process unit can operate successfully under a variety of
            conditions  so  that  the  engineer  must  conduct  studies  to  determine  the  economi-
            cally-optimum operating conditions.  It is clear from  the foregoing  discussion that
            economics determines  the direction taken  at each phase  of  the project.  Conse-
            quently, process  economics  will be  discussed  in the  next  chapter.  It  can  also be
            seen from  Table  1.2 that there  are several social aspects of the process design that
            must  be  considered.  The  effects  of  any possible  emissions  on  the  health  of  the
            workers,  the  surrounding  community,  and  the  environment  must  be  evaluated.
            Even aesthetics will have to be considered to a greater extent than has been done
            in the past.
                 The  next phase  of  the  project  is  plant  design  and  construction,  which  em-
            ploys a variety of engineering skills, mainly mechanical, civil, and electrical.  The
            objective in this phase of the project  is to implement the process design. Table  1.2
            outlines the major  activities of this phase. Most likely a plant design and construc-
            tion company will conduct this phase of the project, commonly called outsourcing.
                 After  the  plant  is  constructed,  the  operations  phase  of  the  project  begins,
            which includes plant startup.  Rarely does this operation proceed smoothly.  Trou-
            bleshooting, process modifications, and repairs are generally required.
                 Because of the need to get the plant on-stream as soon as possible, the proc-
            ess design, plant design, plant construction and plant startup must be completed as
            rapidly  as  possible.  Electrical,  mechanical  or  chemical  systems,  as  well  as  any
            human activity need to be  controlled  or regulated to  approach optimum perform-
            ance.  Similarly,  project  management,  or  more  appropriately  project  control,  is
            needed because  of the  complexity  of process  and plant  design,  and  construction.
            Numerous  activities  must  be  scheduled,  coordinated  and  progress  monitored  to
            complete the project on time.  It is the responsibility of the project  engineer to plan
            and  control  all activities  so that  the plant  is brought  on-stream quickly. It  is poor
            planning to complete the tasks  sequentially, i.e., completing one task before  start-
            ing another task. To reduce the time from the initiation of a project to routine plant
            operation,  the  strategy  is to conduct  as many parallel  activities  as possible.  Thus,
            as many tasks  as possible  are  conducted  simultaneously. This strategy,  illustrated
            in Figur e  1.1 , shows that detailed plant design starts before  completing the process
            design, construction before  completing the plant design, and finally,  startup begins











         Copyright © 2003 by Taylor & Francis Group LLC
   15   16   17   18   19   20   21   22   23   24   25