Page 63 - Chemical process engineering design and economics
P. 63

48                                                       Chapter 2

           simple methods. As the process development advances, then you should use more
           accurate methods.

           DEPRECIABLE CAPITAL COST

           Factor Methods
           Figure  2.4  divides  the  depreciable  capital  costs  into  several  categories.  The  two
           major  categories  are  direct  and  indirect  costs.  Peters  and  Timmerhaus  [4]  and
           Humphreys  [5] list  these  costs.  Reference  [3]  gives  a more  detailed breakdown.
           As Figure 2.4 shows,

                depreciable capital cost =  the cost of:
           delivered equipment
           + equipment placing
           + piping connections between equipment and to utilities
           + electrical equipment and wiring
           + instrumentation and controls
           + buildings
           + auxiliary facilities (offsites)
           + engineering
           + construction contractor's fee
           + contingency                                                 (2.2)
                In  the  factor  methods  for  cost  estimating,  first  calculate  the  purchased  or
           delivered  cost of all major  equipment,  for example,  distillation columns, reactors,
           pumps,  heat  exchangers, etc. Then multiply the total equipment  cost by factors  to
           estimate  the  various  other  components  of  the  depreciable  capital  cost  given  in
           Equation 2.2, such  as piping  and  electrical  wiring.  Thus,  we  arrive  at  the  cost  of
           installing  all  the  equipment  and  supplying  all the  services  needed  to produce  an
           operational process.
                It  helps  to  visualize  the  process  of  constructing  a plant  to  understand  the
           calculation of  depreciable capital cost. First, a purchasing agent orders equipment
           from  various  manufacturers  from  all  over  the  world. The  manufacturers  then  de-
           liver the equipment to the plant site. Shipping charges, insurance,  and taxes add to
           the cost of equipment, resulting in the delivered equipment costs.
                After  arriving  at  the  plant  site,  construction  workers  set  the  equipment  in
           place.  This entails placing the equipment  on  concrete  or  steel  structural supports,
           prepared in advanced.  Because  some equipment could weigh tons, a crane will lift
           the equipment onto  supports. Then, construction  workers secure the equipment in
           place. A factor will account for this cost.
                Next,  pipe  fitters  connect  the  equipment  to  other  equipment  and  to  steam
           and  cooling  water  distribution systems.  Piping and valves, which could weigh




         Copyright © 2003 by Taylor & Francis Group LLC
   58   59   60   61   62   63   64   65   66   67   68