Page 68 - Chemical process engineering design and economics
P. 68

Production and Capital Cost Estimation                         53


            contains factors  for both carbon steel and alloy steel. Alloy steels contain varying
            amounts of  nickel and chromium, such as the stainless steels. The other factors  in
            Table 2.6,  i.e.,  for buildings,  auxiliary  facilities,  indirect  costs,  contractor's  fee,
            and contingency do not depend on the material of construction for a process. As an
            example,  for a carbon-steel,  fluid-processing  plant  constructed at  an existing  site.
            From Table 2.7,  f =  1.86,  and  from Table 2.6,  the  average factor, Z  f r  k = 3.27
                           DC                                      k
            + f DC = 3.27+1.86 = 5.13.
                 The  factors  in  Tables  2.6  and  2.7  are  for  an  average  process  containing
            many pieces-of-equipment  and  should not  be used  for single piece-of-equipment
            and  a  small  installation  containing  only  a  few  pieces-of-equipment.  For  these
            cases, we will use the individual factor method, which will be described next.

            Table 2.6  Cost Factors for Estimating Depreciable Capital Cost -
            Average Factor Method  (Adapted from Reference 4.)___________

                                     Cost Factor, Fraction of Delivered Equipment Cost"
                                     Solids   Solids-Fluid Process  Fluid Process
                                     Process

               Direct Costs
               Delivered Equipment   1.00     1.00             1.00
               Equipment Installation  foe    foe              fee
               See Table 2.7

               Buildings (with services)
               Grass-Roots Plant     0.75     0.52             0.50
               Plant at an Existing Site  0.28  0.32           0.20
               Plant Addition        0.17     0.08             0.07
               Auxiliary Facilities
               Grass-Roots Plant              0.52°
               Plant at an Existing Site"  0.40  0.55          0.70
               Plant Addition        0        0                0

               Indirect Costs
               Engineering           0.33     0.32             0.33
               Construction          0.39     0.34             0.41

               Contractor's Fee 0    0.17     0.18             0.21
               Contingency 6         0.34     0.36             0.42

             i)  Source offactors is Reference 2.4 except where indicated
             >)  Includes installation cost
             ,)  Source: Reference 2.9
              )  5% of direct and indirect costs
              )  1 0% of direct and indirect costs




         Copyright © 2003 by Taylor & Francis Group LLC
   63   64   65   66   67   68   69   70   71   72   73