Page 70 - Chemical process engineering design and economics
P. 70

Production and Capital Cost Estimation                         55


                 The  installation  factor  consists  of  direct  costs,  indirect  costs,  contingency
            cost,  and  a  contractor's  fee. The  installation  factor  for  a  piece-of-equipment  is
            given by

            fi  = foe fie fo                                             (2.4)

            The  direct-cost factor  for equipment, fc, contained in Table 2.8, does not include
                                           D
            buildings and  auxiliary  facilities.  It includes the  labor and materials needed to in-
            stall equipment. The buildings and  auxiliary costs will be  accounted for after  we-
            calculate the depreciable capital cost for equipment.



            EQUIPMENT COST ESTIMATION
            Whether a process engineer uses the average factor method or the individual factor
            method, the major  effort  in estimating the depreciable capital cost is estimating the
            cost  of  equipment.  After  developing  the  process  flow  diagram  and  calculating
            mass and energy flow rates, he can then estimate the size of the equipment and the
            equipment cost. There are three sources of equipment cost data.  These are:  current
            vendor  quotations,  past  vendor  quotations,  and  literature  estimates,  in  order  of
            decreasing accuracy. Woods [10]  has stated that correlation of equipment costs in
            the  literature  can have  large  errors  -  by as much as  100%.  A correlation  with a
            large  error is not completely useless, but it will limit the conclusions that one can
            draw.  Vendor  quotations  are the  most  accurate, but  the  effort  required  to prepare
            detailed specifications  and quotations are not usually warranted in the early stages
            of  a project.  Thus,  we rely  on  literature  estimates  and  past  quotations  for quick
            estimates -  in spite of their lower accuracy.
                 Equipment  costs reported  in the literature are either FOB,  delivered,  or in-
            stalled  cost. Usually, these costs are given at some time in the past. When report-
            ing equipment costs, the date and shipping point should be  specified, but the latter
            is frequently  not given. Shipping cost  (consisting of freight,  taxes, and insurance)
            will  vary  from  10 to  25%  of  the  purchased  cost  [10].  We  will  use  10%,  a value
            recommended by Valle-Riestra  [20].  Then, the delivered cost is

            Csi=1.10C Pi                                                 (2.5)
            Before  adding  equipment  costs they must all be on the same basis -  either  FOB,
            delivered, or installed. For example, Table 2.6 requires that all equipment costs be
            on  the  delivered basis.  If  some  equipment  is reported  on the  installed basis, then
            add this cost after  all other equipment costs are on the installed basis.









         Copyright © 2003 by Taylor & Francis Group LLC
   65   66   67   68   69   70   71   72   73   74   75