Page 83 - Chemical process engineering design and economics
P. 83

68                                                      Chapter 2

            Table 2.14  Calculation  Procedure for Depreciable Capital Cost—
            Average Factor Method____________________________

            1. Obtain purchased-equipment costs for carbon steel at the tabulated size
            and capacity  exponent from Table 2.9.

            2. Calculate the equipment  cost for the required size from  Equation 2.13.1
            in Table 2.13.

            3. Obtain cost indexes from Table 2.12.

            4. Calculate the equipment base cost at the present time, C PB i, from Equa-
            tion 2.13.2.

            5.  Calculate  the  actual  equipment  cost,  C ,  at  the  design  pressure  and
                                                 PAi
            temperature,  material-of-construction,  and  the  required  equipment  design
            from Equation  2.13.3.

            6. Calculate the delivered equipment cost from Equation 2.13.4.

            7. Calculate the average  installation factor for  all equipment, f,, from  Equa-
            tions 2.13.5 and 2.13.6.

            8.  Calculate the  installed equipment cost at actual design conditions,  CSAI.
            from Equation 2.13.7.

            9. Calculate the costs at the base conditions,  CSBI, from Equation 2.13.8.

            10. Specify the process type.

            11.  Obtain  the cost  factors  for  buildings  and  auxiliary facilities  from  Table
            2.6.

            12.  Calculate  the  combined  factors for  buildings  and  auxiliaries, f AB,  from
            Equation 2.13.9.
            13. Calculate  the depreciable capital cost from Equation 2.13.10.