FIGURE 4-19 The Stock/Requirements List screen in SAP ERP
The Stock/Requirements List shown in Figure 4-19 shows purchase orders (POitem),
planned orders (PldOrd), and dependent requirements (DepReq), but it also shows
purchase requisitions (PurRqs). When a planner decides that it is time for a planned order
to become a purchase order, the planned order is converted to a purchase requisition,
which is a request to Purchasing to create a purchase order. The planner can convert a
planned order to a purchase requisition from the Stock/Requirements List screen by
double-clicking the planned order line. This action calls up the Additional Data for MRP
Element window, shown in Figure 4-20.