Page 119 -
P. 119

Production and Supply Chain Management Information Systems
                   start with the weekly master production schedule for NRG-A and NRG-B bars, and then we
                   will complete the following steps:
                           1.  Convert the quantities of NRG bars from cases to 500-pound batches.
                           2.  Multiply the number of batches by the pounds-per-batch quantities (which
                              are given in the BOM) to get the gross requirements for each raw material.    99
                           3.  Subtract the existing raw material inventory and purchase orders that have
                              already been placed from the gross requirements, to determine the net
                              requirements.
                           4.  Plan orders in multiples of the 44,000-pound lot size, allowing for the two-
                              week lead time required for oats, to meet the net requirements in Step 3.
                       These calculations are summarized in Figure 4-17. This view of the data is frequently
                   called an MRP record, which is the standard way of viewing the MRP process on paper.


                    Oats     Lead time = 2 weeks  Week 1  Week 2    Week 3   Week 4    Week 5
                    MPS            NRG-A          984       984      984       984      1037
                    (cases)        NRG-B          422       422      422       422      444
                    MPS            NRG-A          142       142      142       142      149
                    (500 lb. batches)  NRG-B       61       61        61       61        64
                    Gross requirements (lb)      57,850    57,850   57,850    57,850   60,700
                    Scheduled receipts           44,000    44,000
                    Planned receipts                                88,000    44,000   44,000
                    On hand           29,650     15,800    1,950    32,100    18,250    1,550
                    Planned orders               88,000    44,000   44,000
                   Source Line: Course Technology/Cengage Learning.

                   FIGURE 4-17  The MRP record for oats in NRG bars, Weeks 1 through 5

                       The first two rows of the MRP record are the MPS that was the output from the
                   demand management step (shown in Figure 4-14). These NRG production quantities are
                   shown in terms of shipping cases. The first step is to convert the MPS from shipping cases
                   to 500-pound batches. Each shipping case weighs 72 pounds (not including packaging), so
                   to convert shipping cases to 500-pound batches, multiply the number of shipping cases by
                   72 pounds per case, and then divide by 500 pounds per batch. Thus, producing 984
                   shipping cases of NRG-A bars in Week 1 of the year will require 142 batches, as shown in
                   the third row of Figure 4-17.
                       The next row in Figure 4-17 is Gross requirements. The Gross requirements figures
                   are calculated by multiplying the MPS quantity (in production batches) by the pounds of
                   oats needed for a batch of snack bars. Fitter uses 300 pounds of oats per batch of NRG-A
                   bar and 250 pounds of oats per batch of NRG-B bar. This information is derived from the
                   BOM (Figure 4-16). Therefore, for Week 1, Fitter needs:
                           •  NRG-A: 142 batches × 300 lb. per batch = 42,600 lb. oats
                           •  NRG-B: 61 batches × 250 lb. per batch = 15,250 lb. oats
                           •  Total = 57,850 lb. oats
                       The next row in Figure 4-17 is Scheduled receipts. This row shows the expected
                   timing of orders of materials that have already been placed, meaning that the supplier has



                 Copyright 2012 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
               Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
   114   115   116   117   118   119   120   121   122   123   124