Page 178 - Design of Simple and Robust Process Plants
P. 178

5.3 Combination of Process Functions  163
                 In case a gas turbine is not foreseen, the cascade cooling follows the following steps:
                 (i) high-temperature process heating; (ii) medium-temperature process heating; and
                 (iii) air and fuel preheating.
                   In the above process, heating might include steam generation to achieve a correct
                 energy balance. One design for a furnace for high-temperature reactions is that of a
                 calcination reactor (Figure 5.18). The furnace, which is of a staged, fluidized bed



                           Flue Gases
                                                Solids inlet




                 Solids preheating
                 and drying sections



                  Calcination section
                                                  Fuel
                  Air preheating
                  sections

                    Solids outlet
                                           Air inlet

                 Fig. 5.18. Calcination furnace: multi-stage fluidized beds.

                 concept, starts at the cold air side with air preheating stages, and this is followed by
                 calcination with fuel as energy source, together with several preheating zones where
                 the feed material is preheated and dried. Clearly, this design is an example of inte-
                 grated functionality. An overview of the different functions in a furnace are shown
                 in Table 5.4.


                Table 5.4. Combination of functions in a furnace.

                 Furnace                             Application(s)

                 Reaction                            Steam cracker, syngas production
                 High process temperature > 250  C   Process superheater, steam superheater
                 Medium process temperature,         Process heater, evaporator
                 Medium pressure steam
                 Low process temperature < 150  C,   Process heater, condensate heater
                 Low temperature steam
                 Air/fuel preheating                 Flue gas cooling
                 Gas turbine                         Power generation
   173   174   175   176   177   178   179   180   181   182   183