262             Drilling Technology in Nontechnical Language Second Edition






                  Normally, a  BOP  stack would have at  least  one  bag preventer and
              two ram preventers, as shown in figure 11–5. BOP stacks for deeper wells

              might have up to four ram preventers and two annular preventers. The ram
              preventers generally have a higher pressure rating and are always installed
              below the bag preventers. If only two ram preventers are used, the bottom
              set will normally be blind-shear rams, and the upper set will be pipe rams.
              One reason for placing the blind rams on the bottom is that if the pipe

              rams or annular leaks, it is possible to close the blind rams below and fix
              the leak above.
















































              Fig. 11–5. Land rig blowout preventer