                  FLAME CUTTING PIPE—PLAIN ENDS


                               Labor For Straight Pipe Only
                                  Carbon Steel Material

                                NET MAN HOURS EACH
                Standard   Extra Hvy.
       Pipe      Pipe&     Pipe&               SCHEDULE NUMBERS
       Size     O.D. Sizes   O.D. Sizes
      Inches    3/8" Thick   1/2" Thick   20   30   40   60   80   100   120   140   160

     2" or Less   0.09     0.13     -   -   0.09   ..   0.13   -     „   0.18

     2-1/2        0.10     0.15    --   -   0.10   --  0.15   --     --  0.20
     3            0.13     0.18     --  ..   0.13   --  0.18   --  --    0.24
     4            0.18     0.24         --  0.18   --  0.24   --  0.33   0.36
     5            0.21     0.31    --   --  0.21      0.31   --  0.38   ...   0.43
     6            0.29     0.38 '   --  --  0.29   --  0.38   --  0.49   --  0.55
     8            0.40     0.56    0.40   0.40   0.40   0.51   0.56   0.66   0.75   0.84   0.99
     10           0.56     0.80    0.56   0.56   0.56   0.80   0.86   0.95   1.08   1.24   1.50
     12           0.61     0.95    0.61   0.61   0.75   1.13   1.19   1.29   1.50   1.66   1.78
     14O.D,       0.85      1.13   0.85   0.85   1.00   1.25   1.45   1.55   1.70   2.00   2.10
     16 O.D.      0.95      1.40   0.95   0.95   1.40   1.55   1.65   1.85   2.00   2.25   2.55

     18O.D.       1.20     1.70    1.20   1.40   1.70   1.90   2.00   2.25   2.40   2.70   3.15
     20 O.D.      1.45     1.90    1.45   1.95   2.10   2.25   2.40   2.65   2.80   3.25   3.70
     24 O.D.      2.20     2.80    2.20   2.95   3.10   3.25   3.35   3.65   4.05   4.55   5.15

     For mitre cuts less than 30°, add 50% to the above man hours.
     For mitre cuts 30° or greater, add 100% to the above man hours.
     Man hours are for cutting pipe with plain ends only and do not include beveling, threading, etc. See appropriate
     man hour tables for these operations and time requirements.
     For cutting the ends of bends or trimming fittings, add 50% to the above man hours.