Section One-SHOP FABRICATION 41

          FLAME CUTTING LARGE O. D. PIPE—PLAIN ENDS


                                Labor For Straight Pipe Only
                                  Carbon Steel Material

                                 NET MAN HOURS EACH
           O.D.                         WALL THICKNESS IN INCHES
           Pipe
          Inches      .375   .500   .750    1.00   1.25   1.50   1.75   2.00
            26        3.50    4.65   5.25   5.65   5.80   6.10    6.35   6.55
            28        4.05    5.05   5.65   6.10   6.30   6.60    6.70   6.95
            30        4.30    5.45   6.10   6.35   6.70   6.95    7.15   7.45
            32        4.75    5.80   6.40   6.80   7.10   7.45    7.70   7.85
            34        5.20    6.40   6.90   7.30   7.55   7.85    8.15   8.35
            36        5.80   6.95    7.45   7.85   8.15   8.45    8.70   9.00
            38        6.55    7.15   8.05   8.45   8.70   9.10    9.60   9.90
            40        7.30    8.15   8.80   9.05   9.45   9.85   10.25   10.65
            42        8.15   9.30    9.65   9.90   10.25   10.80   11.20   11.55
            44        9.25   10.20   10.65   10.95   11.40   11.75   12.15   12.55
            46        10.35   11.20   11.70   11.95   12.35   12.85   13.30   13.65
            48        11.70   12.30   12.70   13.10   13.50   13.90   14.45   14.80
            54        13.16   13.83   14.28   14.74   15.18   15.63   16.25   16.65
            60        14.62   15.37   15.87   16.37   16.87   17.37   18.06   18.50

                      2.25   2.50   2.75   3.00    3.25   3.50   3.75   4.00
            26        6.90    8.90   9.65   10.40   11.20   12.15   12.70   14.05
            28        7.45   9.45    9.85   10.65   11.50   12.55   13.15   14.40
            30        7.85   9.90   10.20   10.95   12.00   12.95   13.50   14.85
            32        8.30   10.40   10.80   11.40   12.40   13.35   13.90   15.25
            34        8.80   10.95   11.35   11.75   12.90   13.75   14.30   15.65
            36        9.30   11.40   11.80   12.15   13.30   14.30   14.85   16.20

                      4.25   4.50   4.75   5.00    5.25   5.50   5.75   6.00
            26        15.25   16.55   17.75   18.90   20.10   21.35   22.55   23.75
            28       15.65   17.00   18.15   19.45   20.50   21.75   22.95   24.15
            30       16.05   17.30   18.65   19.85   21.00   22.15   23.35   24.55
            32       16.55   17.80   19.05   20.25   21.40   22.60   23.75   25.00
            34       17.00   18.30   19.50   20.65   21.85   23.10   24.30   25.50
            36       17.40   18.75   20.00   21.20   22.40   23.50   24.75   26.05
     For mitre cuts less than 30°, add 50% to the above man hours.
     For mitre cuts 30" or greater, add 100%; to the above man hours.
     Man hours are for cutting pipe with plain ends only and do not include beveling, threading, etc. See appropriate
     man hour tables for these operations and time requirements.
     For cutting the ends of bends or trimming fittings, add 50% to the above man hours.