FLAME BEVELING PIPE FOR WELDING
"V" TYPE BEVELS
Labor For Straight Pipe Only
Carbon Steel Material
NET MAN HOURS EACH
Standard Extra Hvy.
Pipe Pipe& Pipe& SCHEDULE NUMBERS
Size O.D. Sizes O.D. Sizes
Inches 3/8" Thick 1/8" Thick 20 30 40 60 80 100 120 140 160
2" Or Less 0.07 0.10 0.07 .- 0.10 0.14
2-1/2" 0-08 0.12 -- 0.08 0.12 -- 0.16
3 0.10 0.14 - 0.10 0.14 - i 0.19
4 0.14 0.19 .. 0.14 - 0.19 -- 0.26 0.28
5 0.17 0.24 - 0.17 - 0.24 -- 0,30 0,34
6 0.23 0.30 - -- 0.23 - 0.30 0.39 0.43
8 0.32 0.44 0.32 0.32 0.32 0.40 0.44 0.52 0.59 0.65
10 0.44 0.63 0.44 0.44 0.44 0.63 0.68 0.75 0.83
12 0.48 0.75 0.48 0.48 0.59 0.89 0.94 1.03 -- ..
14O.D, 0.67 0.89 0.67 0.67 0.79 0.98 1.14 - .. j
160.D. 0.75 1.10 0.75 0.75 1.10 1.22 1.35 -
18O.D. 0.94 1.34 0.94 1.10 1.34 1.50 -- -- „ j .,
20 O.D. 1.14 1.50 1.14 1.54 1.65 1.82 - --
240.D. 1.73 2.20 1.73 2.32 2.44
_L
For mitre bevels add 50% to the above man hours.
Above man hours are for flame "V" beveling only and do not include cutting or internal machining. See respective
man hour tables for these charges.
For beveling on the ends of bends or shop trimmed fittings, add 50% to the above man hours.
The above man hours are for wall thicknesses of 7/8" or less. For wall thicknesses greater than 7/8" refer to man
hours on following pages.