44   Section One-SHOP FABRICATION

                      CUTTING LARGE O.D. FIFE—PLAIN ENDS

                             Labor For Straight Pipe Only
                                  Carbon Steel Material


                                 NET MAN HOURS EACH
           O.D,                       WALL THICKNESS IN INCHES
           Pipe
           Inches     .375    .500   .750   1.00   1.25   1.50    1.75   2.00
            26         7.77   10.32   11.66   12.54   12.88   13.54   14.10   14.54
            28         8.99   11.21   12.54   13.54   14.10   14.65   14.87   15.43
            30         9.55   12.10   13.54   14.10   14.87   15.43   15.87   16.54
            32        10.55   12.88   14.21   15.10   15.76   16.54   17.09   17.43
            34        11.54   14.21   15.32   16.21   16.76   17.43   18.09   18.54
            36        12.88   15.43   16.54   17.43   18.09   18.76   19.31   19,98
            38        14.54   15.87   17.87   18.76   19.31   20.20   21.31   21.98
            40        16.21   18.09   19.54   20.09   20.98   21.87   22.76   23.64
            42        18.09   20.65   21.42   21.98   22.76   23.98   24.86   25.64
            44        20.54   22.64   23.64   24.31   25.31   26.09   26.97   27.86
            46        22.98   24.86   25.97   26.53   27.42   28.53   29.53   30.30
            48        25.97   27.31   28.19   29.08   29.97   30.86   32.08   32.86
            54        29.22   30.70   31.70   32.72   33.70   34.70   36.08   36.96
            60        32.46   34.12   35.23   36.34   37.45   38.56   40.09   41.07
                      2.25    2.50   2.75   3.00   3,25   3.50   3.75    4.00
            26        15.32   19.76   21.42   23.09   24.86   26.97   28.19   31.19
            28        16.54   20.98   21.87   23.64   25.53   27.86   29.19   31.97
            30        17.43   21.98   22.64   24.31   26.64   28.75   29.97   32.97
            32        18.43   23.09   23.98   25.31   27.53   29.64   30.86   33.86
            34        19.54   24.31   25.20   26.09   28.64   30.53   31.75   34.74
            36        20.65   25.31   26.20   26.97   29.52   31.75   32.97   35.96
                      4.25   4.50    4.75   5.00   5.25   5.50   5.75    6.00
            26        33.86   36.74   39.41   41.96   44.62   47.40   50.06   52.73
            28        34.74   37.74   40.29   43.18   45.51   48.29   50.95   53.61
            30        35.63   38.41   41.40   44.07   46.62   49.17   51.84   54.50
            32        36.74   39.52   42.29   44.96   47.51   50.17   52.73   55.50
            34        37.74   40.63   43.29   45.84   48.51   51.28   53.95   56.61
            36        38.63   41.63   44.40   47.06   49.73   52.17   54.95   57.83

      For mitre cuts less than 30", add 50% to the above man hours.
                C
      For mitre cuts 30  or greater, add 100% to the above man hours.
      Man hours are for cutting pipe with plain ends only and do not include beveling, threading, etc. See appropriate
      man hour tables for these operations and time requirements.
      For cutting the ends of bends or trimming fittings, add 50% to the above man hours.