Page 224 - Estimators Piping Man Hour Manual
P. 224

Section Nine—INSULATION       207

                                INSULATION


                              HOT  PIPING  —  MAN HOURS
                                               Screwed           Flanged
             Pipe                     Straight  &  Weld          Valves
             Size                       Pipe   Fittings  Flanges  fc Fittings
            Inches  Thickness and Type  per  1. f.  per each  per  pair  each
            1/2     1" thick Calsilite  .11      .14      .36      .74
            3/4     1" thick Calsilite  .11      .15      .36      .74
            1       1" thick Calsilite  .12      .18      .36      .74
            1-1/2   1" thick Calsilite  .13      .21      .41      .83
            2       1" thick Calsilite  .14      .22      .44      .88
            3       1" thick Calsilite  .18      .27      .54     1.37

            4       1" thick Calsilite  .21      .34      .65     1.65
            5       1" thick Calsilite  .25      .52      .72     2.05
            6       1" thick Calsilite  .25      .61      .77     2.15
            7       1-1/2" thick Calsilite  .33  .93      .96     2.96
            8       1-1/2" thick Calsilite  .36  1.18    1.10     3.39

     Man  Hour;
         1.  Above thicknesses and man hours  are  for  all  hot services, if calcium  silicate is  used.
         2.  The above man hours are  for  either  indoor or  outdoor service.
        3.  Bent Pipe:  1.5 x straight pipe of like size and thickness  measured  along outside radius.
        4.  Steam  Traced  Piping:  To  be  man  houred  at  size  of  pipe  covering required to fit over
            pipe and tracer  line.
         5.  Method  of  Measurement:  Straight pipe to be determined by measuring along approximate
            center  line over  the exterior of the insulation  from  center line to center  line of change
            of  direction.  Measurement shall be made through  all  valves  and  fittings,  except  bent
            pipe.
        6.  Specifications:
            a.  Pipe  Covering: Molded sections secured  with 16 ga. galvanized tie wire,  finish:  In-
              doors  with  6  ounce canvas  with  laps sealed with Arabol lagging adhesive.  Finish:
              Outdoors with  55# Fiberock  Asbestos  Roofing  felt  secured with 16 ga. galvanized  tie
              wire 6" o. c.
            b.  Fittings:  To be built-up with insulating cement or  sectional pipe covering pointed up
              with  asbestos  cement, finished  with  6  ounce canvas and Arabel for  indoor service
              and  "Seal Perm"  for outdoor service.