Page 220 - Estimators Piping Man Hour Manual
P. 220

Section           Eight


                               PATENT

                               SCAFFOLDINO





                               This  section  covers labor  in man hours  for  the
                               erection and  dismantling  of patent tubular  steel
                               type scaffolding.


                               In  the  process  of  making  the  piping  material
                               take-off, the estimator should give due consider-
                               ation to the  lengths  of  run,  the  height, etc.,  so
                               that  the  number  and  height  of sections  of  scaf-
                               folding  may be determined  for  the  entire piping
                               job.

                               We  have  not  attempted  to  cover  job  fabricated
                               homemade   scaffolding due  to  the  fact  that this
                               type  of  scaffolding  for  a  piping  job  is  so  out-
                               rageously  high. If this type of scaffolding is  de-
                               sired,  you  must  look  elsewhere  or  draw from
                               your past  experience.