Section Eight
PATENT
SCAFFOLDINO
This section covers labor in man hours for the
erection and dismantling of patent tubular steel
type scaffolding.
In the process of making the piping material
take-off, the estimator should give due consider-
ation to the lengths of run, the height, etc., so
that the number and height of sections of scaf-
folding may be determined for the entire piping
job.
We have not attempted to cover job fabricated
homemade scaffolding due to the fact that this
type of scaffolding for a piping job is so out-
rageously high. If this type of scaffolding is de-
sired, you must look elsewhere or draw from
your past experience.