Section Ten











                    This  section  is  presented  for  the  purpose  of  showing the
                    work  ability  of  a  few  of  the  man  hour  charts  as  appear
                    throughout  this  manual.  It  does  not  mean  that  a  take-off
                    must  be  made  in  this  manner  before  the  man hour charts
                    will work.  It is  merely  a suggested  method.

                    You  will  note  on  the  following  take-off  sheets at  the  top of
                    the page a predetermined composite rate, arrived at as  out-
                    lined  in the  Introduction  of this manual. Simply by multiply-
                    ing  this  composite  rate  by  the  total man hours  involved, a
                    total  estimated  direct  labor  dollar  value can be easily and
                    accurately  obtained.

                    We  do  not  show  in this sample  estimate any material cost,
                    nevertheless, you  will  find  ample  space  provided  for  this
                    item.  You will  also  find  space  provided  for  both unit and
                    total weights of pipe  and fittings.  We feel that this item  has
                    much   value  such  as  an  estimate  check  using  the  weight
                    method,  or  for  the  estimation  of  warehousing,  equipment
                    usage  and fabrication  shop set-up.

                    We  purposely  have  not  included  material,  miscellaneous
                    supplies, equipment usage,  overhead  and profit  in this esti-
                    mate.  As  is  stated  in  the  Preface  of  this manual, its  sole
                    purpose  is  for  the  estimation  of direct  labor  in man hours
                    only.