Page 45 - Failure Analysis Case Studies II
P. 45

Failure Analysis Case Studies I1
                  D.R.H.  Jones (Editor)
                  8 2001 Elsevier Science Ltd.  All rights reserved                         31





                           FAILURE  OF  A  FLEXIBLE PIPE WITH  A  CONCRETE
                                                     LINER


                                      MARK TALESNICK* and RAFAEL BAKER
                           Department of Civil Engineering, Technion, Israel Institute of Technology, Haifa 32000, Israel
                                               (Received I5 Sepfember 1997)
                       Abstract-This  study documents the functional failure of a concrctc lined steel sewage pipe. Symptoms of the
                       pipe  failure are presented.  Failure  of  the pipe system can  be  attributed  to incompatibility between  the
                       mechanical behavior of the pipe and the methodology employed in its design. The underlying cause of the
                       failure may be traced to a lack of sufficient backfill stiffness. In situ testing was used  to evaluate the stiffness
                       of  the side backfill. The existing pipe-trench  system condition was analysed  numerically and  a criterion
                       developed for the consideration of the structural integrity of the pipeline. 0 1998 Elscvicr Science Ltd. All
                       rights reserved.
                       Keywords: Corrosion protection, fitness for purpose, pipeline failures.


                                               1.  INTRODUCTION

                  The present paper documents a failure of a large diameter concrete lined steel sewage pipe, buried
                  in a clay soil profile. The project consisted of a 3.5 km long gravity pipe in central Israel which
                  failed before being placed in service. The present contribution documents the failure of  this pipe-
                   trench system. Field and laboratory testing provided significant insight into the probable cause(s)
                  of failure. The case study accentuates some basic design principles, as well as the use of simple field
                  tests as an effective diagnostic tool to evaluate site conditions.


                               2.  DESIGN,  CONSTRUCTION  AND  SITE CONDITIONS
                    The sewage pipeline was designed and constructed in central Israel during 1992-1994. The design
                  called for a steel pipe with an inner diameter of 120 cm and a wall thickness of 0.64 cm. The inner
                  surface of the pipe was lined with an aluminum based cement of between 1.8 and 2.2 cm thickness.
                  The primary purpose of the inner liner was to provide protection of the steel pipe from the affects
                  of the corrosive sewage flowing inside. The outer surface of the pipe was covered by a 2.5 cm thick
                  concrete layer.
                    The design of  the pipe-trench  system was based on a flexible pipe criterion. This implies that
                  the pipe maintains  structural and  functional  integrity by  mobilizing lateral  resistance from  the
                  surrounding soil. The pipe was designed to withstand static soil loads alone.
                    A design section of the piptrench system is shown schematically in Fig. 1. The pipe invert was
                  founded at a depth of between 4.5 and 5.5 m below the ground surface, depending on the natural
                  topography. The natural soil consists of a highly plastic clay (CH, liquid limit: o, = 62%, plasticity
                  index: Ip = 36%). A perched water table (depths of as little as 2-3  m) exists in part of the project
                  area. The design specified the excavation of a 2.5 m wide trench (twice the pipe diameter), placement
                  of a 20 cm thick layer of poorly graded gravel (GP) with a particle size between 16 and 20 mm. The
                  pipe was placed directly on the gravel layer. Following placement of  the pipe section the design
                   specified that (a) dune sand (SP) with calcareous concretions (Dso = 0.17 mm and D,,, = 0.12 mm)
                   be placed around the pipe to a height of 30 cm  above the pipe crown elevation; (b) above that


                     Author to whom correspondence should be addressed.
                  Reprinted from Engineering Failure Analysis 5 (3), 247-259 (1998)
   40   41   42   43   44   45   46   47   48   49   50