Page 235 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 235

Compressor Best Practices   Best Practice 3 .24
              from the improper design of the lube system, seal system  the operating discharge pressure is above 3,450 kPa (500 psi))
              separation labyrinth. In addition to the above considerations,  should always be conducted when retrofitting from liquid to
              a critical speed analysis, rotor response and stability analysis (if  dry gas seals.







               Best
               Best Practice 3.24Practice 3.24Practice 3.24
               Best
               For operating pressures above 13,800 kPa (2,000 psi), re-  Lessons Learned
               quire full pressure and full load centrifugal compressor  Correcting a gas disturbance problem in the field can
               shop testing only if the vendor does not have 2 years’ op-  result in long operational delays (weeks), losses of millions
               erating field experience on similar gases at the pressure  of dollars of revenue and may require multiple field
               levels specified.                                    modifications.
                  At high field operating pressures >13,800 kPa (2,000 psi), gas
               disturbances can result in serious operational problems and prevent  Benchmarks
               continued operation.                                This best practice has been used since 1990. Very few full pressure and
                  Since high pressure gas densities will cause these issues, be sure  full load tests are necessary today if vendors are selected who have
               to specify a full pressure and load shop test and not only a full load test  high pressure field operating experience.
               which may not match field pressure levels, if the vendor cannot show
               field operating experience at the specified pressure levels.


              B.P. 3.24. Supporting Material                       there certainly are many opportunities to ensure equipment re-
                                                                   liability during shop test, but there are also a lot of potential lost
              If a full pressure and load test is required, justify the full pres-  opportunities if they are not justified to the project team early,
              sure test on the basis of a minimum of two weeks of lost pro-  during the pre-FEED phase of the project. The potential lost shop
              duction in the first year of plant operation.         test phase opportunities are noted in Figure 3.24.2.

              Testing phase
                                                                    The following opportunities will be lost if they are not justified at
                                                                    project inception:
              The testing phase is the last phase in terms of vendor and sub-  Possible full load test
              supplier design and manufacturing involvement in the project;  Unproven component tests
              and it is the last chance to ensure the optimum availability of the  Attendance at test by plant personnel
              finished product.                                        Use of special tools
                Remember that all of the equipment addressed in this section  Vendor permission for pictures
              is most likely custom designed, and no matter how much ac-  Agreement that assigned vendor field service specialists will be
              crued design and manufacturing experience is present, the  present for tests
                                                                      Agreement that the instruction book is reviewed
              possibility of some abnormality, hopefully minor, is high.  Agreement for formal field construction meeting to clearly
              Therefore, it is imperative that this phase be carefully observed  define all vendor procedures from receipt of equipment on site
              and witnessed by the end user team. Figure 3.24.1 lists impor-  to initial run in of equipment
              tant facts surrounding this phase of the project.
                                                                   Fig 3.24.2   Potential lost test opportunities
               The shop test is an opportunity to:
                                                                     The success of the shop test depends on a good test plan that
                  Confirm vendor proper design and manufacture
                                                                   is reviewed by the end user and contractor and modified as
                  To match field conditions
                                                                   requested, well in advance of the test. Figure 3.24.3 presents
                  To witness assembly and disassembly using job special tools
                  To have plant personnel observe test, assembly, etc. and take  these facts.
                  pictures for purposes of emergency field maintenance
                  excellence
                  Review the instruction book                          The agenda is issued for review 2 months prior to test
                  Have the assigned vendor service engineer observe the  It incorporates agreed VCM scope
                  equipment he will install                            Compressor performance test conditions are per ASME PTC-
                  Review all vendor field procedures                    10 requirements
                                                                       A sample of test calculations and report format is included
                                                                       Vendor concurs with all end user and contractor comments
              Fig 3.24.1   The shop test                               prior to test
                A shop test checklist is included at the end of this B.P. that will
              be valuable for planning and executing the shop test phase. Yes e  Fig 3.24.3   Shop test agenda review e key facts

                                                                                                               209
   230   231   232   233   234   235   236   237   238   239   240