Page 236 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 236

Be st Practice 3 .24          Compressor Best Practices
          I began my career in rotating equipment on the test floor, and
       I can still remember how we would see the witnesses come in  Per ASME PTC-10 requirements
       with an intent to completely participate in the entire test only to  Reconfirm test speed is per PTC-10
       leave for a long ‘test lunch’ an hour or so later. Why did this  Confirm all instruments are calibrated and installed
       occur? Usually because the concerned end user and contractor  Confirm test gas purity
       witnesses did not have the opportunity to review the test set-up  Agree that conditions are stable prior to each test point
       and the procedure prior to the test. As a result, I have always  Confirm vendor's calculations for each test point
                                                                Do not accept until all test requirements are met
       been a proponent of a pre-test meeting.
          Is it always required? I think it is, but the detail and timing of
       the meeting depends on certain factors, noted in Figure 3.24.4.  Fig 3.24.8   Compressor performance test e key facts


                                                              At the conclusion of all test activities, there is still important
                                                            work to be performed. These items are defined in Figure 3.24.9.
           If the equipment is prototype
           If the equipment is complex
           If a full load test is required
           If the test facility is new
                                                                Confirm performance results, corrected to field conditions
                                                                Confirm mechanical test acceptance
       Fig 3.24.4   When is a pre-test meeting required?
                                                                Confirm auxiliary system test acceptance
                                                                Inspect components and confirm acceptance
          If it is decided to conduct a pre-test meeting, the key facts are  Agree to any corrective action in writing
       noted in Figure 3.24.5.                                  Accept or reject test – any corrective action requires a retest!

                                                            Fig 3.24.9   Post test e key facts
           Conduct the meeting prior to the test day
           Send the agenda to the vendor well in advance      What happens if the test is not successful? Approximately
           A typical agenda outline:                        50% of the tests that I have either run or participated in over my
           •  Confirm test agenda requirements
                                                            career have not been successful in regards to one component or
           •  Confirm all test parameter acceptance limits
           •  Confirm instrument calibration                 more not meeting test requirements. Possible rejected test
           •  Review test set-up or concept drawing         action is noted in Figure 3.24.10.
           •  Review data reduction methods
           •  Confirm all test program agreements

                                                                Immediately provide details to the project team
       Fig 3.24.5   Pre-test meeting e key facts                Confirm if field conditions can handle the abnormality
                                                                Determine if the ‘as tested’ machine will meet all reliability
                                                                requirements
          Figures 3.24.6 to 3.24.8 define recommended test activity for  If the decision is to reject, inform the vendor and detail the
       the mechanical, auxiliary equipment and performance shop  reasons
       tests respectively.                                      Do not accept unrealistic delivery delays


                                                            Fig 3.24.10   Rejected test action
           Per API and project requirements
           Confirm all components are installed                Finally, do not forget the importance of test report re-
           Confirm all accessories are installed             quirements. The test report is a most important document that
           Monitor progress of test, look for leaks, etc.
           Do not accept test until all requirements are met  represents the ‘baseline performance of the unit’ and will be
                                                            a benchmark for field operation acceptability. Test report e key
                                                            facts are noted in Figure 3.24.11.
       Fig 3.24.6   Mechanical test e key facts

                                                                The shop test is the field baseline!
                                                                The test report must be detailed and complete
           Must be per API and project requirements             Review the preliminary contents of the report before leaving the
           Confirm that the test agenda is followed              test floor
           Confirm all components are installed                  Obtain the actual test results
           Confirm that all required instruments are installed   When the final report is received, check the results obtained at
           Monitor the progress of the test – look for leaks, etc  test against the final report
           Do not accept until all requirements are met         Immediately contact the vendor if there are any differences

       Fig 3.24.7   Auxiliary system test e key facts       Fig 3.24.11   Test report e key facts

           210
   231   232   233   234   235   236   237   238   239   240   241