Page 154 - Global Project Management Handbook
P. 154

7-4           STATE OF THE ART OF GLOBAL PROJECT MANAGEMENT

        controlled, and closed down. Because of its great importance, program marketing
        should be seen as its own subprocess of program management and not—as in project
        management—as a part of the start, control and close-down processes.
           The assignment of a program to a program manager by the program owner team is the
        starting event of a program. Program approval by the program owner team is the formal
        program close-down (Fig. 7.4).
           Program management is to be performed in addition to management of the individual
        projects that make up the program. Instruments for integrating projects into a program are
        the planning and control of program objectives, the program schedule, the program bud-
        get and the program risk, the design of the program environment relationships, and the
        design of the program organization and of the program culture. It is to be ensured that the
        projects follow the program standards. The projects of a program are closely coupled by
        fulfilling program management functions.


        Program Management Subprocesses
        The program start and program close-down processes are limited in time and are
        performed only once in a program, but the program control process in a program is
        performed several times. Program coordination and program marketing are continuous
        processes.
           As an example of the description of the subprocesses of program management, the
        objectives and time boundaries of the program start process are listed in Table 7.1, and
        the tasks and responsibilities are described in Fig. 7.5.



                Program
               assignment



              Program start

            Program controlling
                                     Continuous            Program
                                 program coordination      marketing
           Resolving a program
              discontinuity


           Program close-down




                Program
                approved

         FIGURE 7.4  The program management process.
   149   150   151   152   153   154   155   156   157   158   159