Page 417 - Global Project Management Handbook
P. 417

20-6           MANAGEMENT OF THE PROJECT-ORIENTED COMPANY

        The European Construction Institute (2003) defines long-term partnering as

             . . . the development of sustainable relationships between two or more organizations,
           to work in cooperation for their mutual benefit in the requisition and delivery of works,
           goods and/or services over a specified period to achieve continuous performance
           improvement.

        In the next two sections I consider each of these forms of partnering in turn.


        SINGLE-PROJECT PARTNERING

        Why and When to Adopt Partnering

        As we have already seen, partnering is adopted to overcome limitations in traditional
        contracting. Two of these limitations have been discussed already:
        ● Misalignment between the client’s and the contractor’s objectives
        ● Misalignment between the various contractors objectives
           Another reason is to gain early access to contractor expertise. A problem with tradi-
        tional contracting is that the construction contractor is only appointed when construction
        is about to start, which means that the contractor’s construction expertise is not available
        to the design team to improve the constructability of the plant. Improving constructability
        can help to reduce construction costs. Under traditional contracting, the construction con-
        tractor is not appointed until the design is complete, but then it is too late to gain access
        to that contractor’s expertise. Under a traditional contract, if the construction contractor is
        appointed before design is complete, during construction, the contractor will be seeking
        variations (see Fig. 20.1, left) to cover the uncertainties in the design that existed when
        the contractor was appointed. Under alliancing, the contractor is appointed early to help
        reduce the cost of construction, and the contractor’s share of the gain-share pot covers the
        uncertainties in design that exist when the contractor is appointed.
           Scott (2001) illustrates what can be achieved with partnering and alliancing

        (Table 20.1). The first column is the forecast cost of the project at concept stage, when
        most of the contractors are appointed. The second column is the estimated cost at sanction,
        and the third column is the outturn cost. The difference between the first and second col-
        umn is primarily reductions in the cost of works from early access to contractor expertise,



        TABLE 20.1  Savings from Project Partnering

        Project               Concept Estimate  Sanction Value    Out-turn
        Off-shore oil platform  £450 million     £373 million    £290 million
        Refinery revamp                          $295 million    $269 million
        Plant addition         $175 million      $149 million    $133 million
        Onshore terminal       £123 million      £119 million     £92 million
        Off shore pipeline     £348 million      £319 million    £242 million
        Hydrocracker revamp                       £41 million     £39 million
        FCCU revamp                               £54 million     £47 million
   412   413   414   415   416   417   418   419   420   421   422