Page 414 - Global Project Management Handbook
P. 414

PARTNERING IN PROJECTS               20-3

        be a company (contractor) rather than a person, what the Dutch would call a “legal person”
        rather than a “natural person.” However, the owner should view these legal persons as
        much as his or her employees as natural persons and motivate them to achieve their proj-
        ect objectives.
           Levitt and March (1995) say the following about the purpose of organizing:

           The problem of organizing [is] seen as one of transforming a conflict (political) system
           into a cooperative (rational) one. A conflict system is one in which individuals have
           objectives that are not jointly consistent. It organizes through exchanges and other inter-
           actions between strategic actors. A cooperative system is one in which individuals act
           rationally in the name of a common objective.

           The aim of project organization should be to create a cooperative system in which
        individuals, legal persons and natural persons, work together in a rational way to achieve
        a common (the owner’s) objective. The owner should try to motivate the contractors to
        achieve his or her objectives, and it is widely recognized that this is best done through a
        win-win game. Turner and Müller (2004) actually have shown that cooperative working
        on projects improves project performance; cooperative working is a necessary condition
        for project success. They defined cooperative working on projects as
        ● Having common, well-defined objectives
        ● Working together in a spirit of cooperation and partnership
           Unfortunately, throughout the latter half of the twentieth century, the norm has been
        the alternative approach—to view the project as a competition in which only one party
        can be the victor, the contractor or the client. I can speculate why this might be. One rea-
        son is almost certainly that the client and project manager are in a principal-agent rela-
        tionship (Turner and Müller, 2004; Jensen, 2000), in which the project manager has more
        information about project progress and the factors influencing project performance than
        does the client, leading to discomfort and mistrust on the latter’s part. Turner and Müller
        (2004) have suggested communication mechanisms to reduce this discomfort. Another
        reason is the result of bounded rationality. Even though the project manager might like to
        achieve the client’s objectives, through human frailty, he or she cannot do so perfectly
        because

        ● The project manager does not have perfect information about the client’s require-
          ments of project performance.
        ● The information the project manager does have he or she cannot process perfectly.
        ● The project manager cannot foretell the future and so cannot forecast all the risks and
          issues that will be encountered.

           This leads the project manager to “satisfice”—to do what is adequate in the circum-
        stances, not what is perfect.
           Thus the aim of the project organization should be to develop a cooperative working
        relationship between the client and the project manager or between the client and the con-
        tractor. Where the client and project manager work for separate legal entities, the project
        contract is a key governance mechanism for project organization. Thus, to achieve coop-
        erative working, we need forms of contracts that encourage it, and project partnering is
        one such form. However, before describing project partnering, I wish to consider how
        attitudes toward risk sharing on project contracts changed throughout the last two decades
        of the twentieth century.
   409   410   411   412   413   414   415   416   417   418   419