Page 154 -
P. 154

128  •  Green Project Management



             is assessing. As the milestone approaches, the project manager can use a
             metric of completion to give an indication of project progress. And if it
             gets to the point where the milestone is not met, it gives the project team
             a chance to look at all of the constraints and consider replanning. In our
             example, the team may want to revisit the cost and quality of the packag-
             ing at that point in time. The more critical the task, the more frequent and
             well-publicized the milestones should be. This is particularly true with
             the green aspects of the project. Because they are relatively new tasks to
             the project, they should be monitored more closely. Any trade-offs of the
             green aspect of the packaging to gain time or reduce costs should be vetted
             against the environmental management plan. Here’s where the vigilance
             piece  comes  in  for  greenality—it’s  the  difference  between  monitor  and
             control versus monitor and sigh. Another observation tool is the Earned
             Environmental Management System, a system outlined in the following
             paragraphs that can help to determine if there are any variances in par-
             ticular aspects of the project’s greenality. The observation of the health of
             the project’s green aspects, as well as the health of other project aspects, is
             critical to the success of the project. The aim of conscientious observation
             is to catch issues that arise while there is still time to do something about
             them, even if it means terminating the project. Those familiar with large
             government  projects  are  probably  aware  of  the  macabre  statistics  that
             indicate that even with only 20% of the project complete, if you are behind
             schedule or above budget, those aspects will likely never recover.
              The process of greenality data analysis involves collecting relevant data
             about the project’s greenality efforts and then analyzing it, seeking some
             reference point as to how effective the efforts have been, if they are being
             maintained, and deciding whether or not any “course corrections” need
             to be completed. The data supplied in the process can come from a vari-
             ety of qualitative and quantitative techniques. Some of the data inputs are
             relatively accessible. The project’s planned schedule and budget are used in
             the variance analysis process of earned value management (EVM). EVM
             is not intended to provide detail as to what actions should be taken on a
             project, but is designed to provide a measurement of whether or not there
             are any variances in schedule and costs at any point in project execution.
             Remember what we said earlier about advancing data into information,
             knowledge, and wisdom? Earned value is a way to do that. See the vignette
             “A Case for Earned Value” at the end of this chapter for an example of
             why you’d want to use it. In any case, the earned value technique uses as
             variables earned value (EV) and actual costs (AC) to determine if there is
   149   150   151   152   153   154   155   156   157   158   159