Page 167 -
P. 167

Taking the Watch (Monitoring and Controlling)  •  141



                 •   Cost variance (CV) = EV – AC = $4,000 – $6,500 = –$2,500

              We are over budget by $2,500!


                 •   Schedule variance (SV) = EV – PV = $4,000 – $5,000 = –$1,000

              We are behind schedule by $1,000 (a peculiar way to state schedule, but
              a standard one).

                 •   Cost performance index (CPI) = EV/AC = $4,000/$6,500 = 0.6153


              For each dollar we spent, we are getting only about 62 cents worth of
              accomplishment.

                 •   Schedule performance index (SPI) = EV/PV = $4,000/$5,000 = 0.8


              For each hour we put in, we are completing only 80% of what we had
              planned.


              It’s beyond the scope of this book, but we can also use these figures
              to forecast the completion figures for the project. In this case, for
              example,  we can  take  our  budget  at  completion (BAC)  of  $10,000
              and divide by the CPI to get our estimate at completion (EAC) to
              predict our final project cost, given the data at our halfway point.
              That would be:

                 •   EAC = BAC/CPI = $10,000/0.6153 = $16,252




             endnotes

                1.  Robert K. Wysocki, Robert Beck Jr., and David Beck, Effective Project Management,
                 2nd ed., (New York: Wiley, 2000).
                2.  Alexander Laufer, “Managing Projects in a Dynamic Environment: Results-Focused
                 Leadership,”   http://askmagazine.nasa.gov/pdf/pdf19/105553main_19_resources_
                 letterfromeditor.pdf.
   162   163   164   165   166   167   168   169   170   171   172