A potential hydroelectric site has an estimated maximum static head for the

               hydroturbines  of  300  ft  (91.4  m),  between  the  water  source  and  the
               downstream pool. Average conduit flow of the water to the turbines is 575
                                                                                     3
                              3
               cfs  (16.3  m /s);  maximum  flow  rate  is  675  cfs  (19.1  m /s).  Determine  the
               practical  power  output  of  this  potential  hydro  site.  Evaluate  the  various
               factors  that  must  be  considered  to  make  the  site  economically  feasible.
               Figures 5 through 8 show possible turbine choices.



























                          FIGURE 5 Cross section of an impulse (Pelton) type of hydraulic-
                     turbine installation.