Page 393 - High Power Laser Handbook
P. 393

362    So l i d - S t at e   La s e r s                                                                          The National Ignition Facility Laser    363


                         The  Ligne  d’Integration  Laser  (LIL)  was  completed  in  2002  at
                      Cesta,  France,  by  the  French  nuclear  science  directorate  Commis-
                      sariat à l’Énergie Atomique (CEA). This four-beam prototype of the
                      240-beam Laser Mégajoule (LMJ) was designed, like NIF, to be capa-
                      ble of demonstrating inertial fusion ignition and gain. There has been
                      very active collaboration between NIF and LMJ designers, and we
                      have learned much from each other. A notable example is the devel-
                      opment at CEA of programmable spatial light modulators for detailed
                                                                          24
                      tailoring of the light that is launched into the large amplifiers.  As of
                      this writing, NIF is in the process of installing these devices in the
                      front end of all beamlines.
                         NIF is the culmination of the experience gained at all of these facili-
                      ties over the years. Its fundamental requirements in terms of energy,
                      power,  pulse-shaping  finesse,  far-field  spot-size  control,  power
                      balance, and shot-to-shot reproducibility, among other criteria, were
                                    25
                      laid out in 1994.  Its goal is to achieve fusion breakeven, with more
                      thermonuclear energy released than is delivered in the form of laser
                      energy, based on the understanding that has been developed by the
                      plasma-physics  and  target-coupling  data  gathered  in  previous
                      facilities.
                         Ceremonial groundbreaking occurred in May 1997, and by June
                      1999, the stadium-sized facility was sufficiently completed that the
                      10-m, 264,000-lb target chamber could be installed in the target bay.
                      The conventional facility was completed in September 2001, and in
                      December 2002, its first four beams were fired at 43-kJ IR in a 5-ns
                      pulse. On May 30, 2003, NIF set the first of its world records by firing
                      a single-beam 10.4-kJ, 3.5-ns UV pulse into its precision diagnostics
                      system, thus meeting its primary criteria for beam energy, uniformity,
                      and pulse-shaping capability. The first plasma-coupling experiments
                      were carried out in August 2003. On February 24 and 25, 2009, a spe-
                      cial subcommittee of the National Ignition Campaign (NIC) Review
                      Committee met with NIF scientists for “a formal performance review
                      of the status of the Laser System of NIF and the readiness of the Laser
                      System  for  its  role  in  the  National  Ignition  Campaign.”   Their
                                                                         26
                      conclusion was “that each and every one of the laser performance
                      Completion Criteria, established under the NIF Project Completion
                      Criteria, has been met or exceeded.” 26


                 14.3  NIF Facility and Laser Overview
                      For more than a decade, up to 1000 engineers, scientists, technicians,
                      and skilled laborers, as well as more than 2300 vendors, have worked
                      on NIF. NIF’s 192-laser beamlines are housed in a building with a volume
                      of about 350,000 m . Figure 14.1 shows an aerial photograph of the NIF
                                     3
                      site, doctored to remove the roofs and to show the internal structure. In
                      the upper left is the optical assembly building, where final assembly,
   388   389   390   391   392   393   394   395   396   397   398