Page 283 - Hydrocarbon Exploration and Production Second Edition
P. 283

270                                                     Oil and Gas Processing


                Gas / Oil from                   Seperator Gas
                 Production                          to
                                          7
                  Manifold                       Compression
                                   2
                    1
                                  V-101   LC
                         LC
                            INT
                                                 To Flare
                             4       3
                                               5


                                              V-102        LC
                                                                     Stabilised
                          Produced                       6           Crude to
                          Water to                                    Storage
                         Treatment
                                                 P-101
          Figure 11.3  Main process £ow scheme (PFS).


            preparing a preliminary plant layout
            supporting early cost estimates (25–40% accuracy)
            preparing engineering design sheets
            basic risk analysis.


             Detailed engineering design work and preparation of utilities and safety
          flow schemes will often require input from specialist engineering disciplines such
          as rotating equipment engineers, and instrument and control engineers. It is
          common for oil and gas companies to contract out the detailed engineering
          design and construction work once preliminary designs have been accepted.
          Utilities refer to support systems such as power, instrumentation, water and safety
          systems.
             Once the main components of the PFS have been selected, the process
          engineer will perform a preliminary simulation to see whether the process works
          ‘on paper’. This identifies the points at which the flow stream needs, for example,
          temperature or pressure elevation and second-order pieces of equipment, such as
          heaters and pumps can be added where appropriate. A process simulation is usually
          run under a range of operating conditions from start to end of the field life cycle.
          A check will also be made to ensure that flow will start up again after a plant
          shutdown.
             The diagram given in Figure 11.4 will be discussed in more detail in Chapter 13,
          but is included here to introduce the different phases of a project, and the
          corresponding levels of design detail.
   278   279   280   281   282   283   284   285   286   287   288